Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
40
matching recommendationsSIC | 339 | Miscellaneous Primary Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0176 # 06 Y:2000 | 06 | 2000 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $425,187 | $800,000 | Not Implemented |
UM0176 # 05 Y:2000 | 05 | 2000 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $51,717 | $8,050 | Not Implemented |
UM0176 # 04 Y:2000 | 04 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $127,531 | $162,750 | Not Implemented |
UM0176 # 03 Y:2000 | 03 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,038 | $2,201 | Not Implemented |
UM0176 # 02 Y:2000 | 02 | 2000 | INCREASE AMOUNT OF CONDENSATE RETURNED | $72,582 | $15,000 | Not Implemented |
UM0176 # 01 Y:2000 | 01 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $733 | $500 | Not Implemented |
HO0232 # 07 Y:2000 | 07 | 2000 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $18,455 | $60,000 | Not Implemented |
HO0232 # 10 Y:2000 | 10 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $61,200 | $640 | Not Implemented |
HO0232 # 06 Y:2000 | 06 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,237 | $1,200 | Not Implemented |
HO0232 # 05 Y:2000 | 05 | 2000 | USE COMPRESSOR AIR FILTERS | $2,211 | $150 | Not Implemented |
HO0232 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $252 | $600 | Not Implemented |
HO0232 # 03 Y:2000 | 03 | 2000 | INSTALL OCCUPANCY SENSORS | $11,219 | $2,000 | Not Implemented |
HO0232 # 02 Y:2000 | 02 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,004 | $0 | Not Implemented |
HO0232 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,133 | $35,343 | Implemented |
HO0232 # 19 Y:2000 | 19 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $5,360 | $6,240 | Not Implemented |
HO0232 # 18 Y:2000 | 18 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,500 | $368 | Not Implemented |
HO0232 # 17 Y:2000 | 17 | 2000 | INSTALL SHROUDING ON MACHINES TO PREVENT SPLASHING | $2,295 | $2,000 | Not Implemented |
HO0232 # 16 Y:2000 | 16 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $16,380 | $0 | Not Implemented |
HO0232 # 15 Y:2000 | 15 | 2000 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $7,800 | $5,000 | Not Implemented |
HO0232 # 14 Y:2000 | 14 | 2000 | CLEAR AND RENT EXISTING SPACE | $341,986 | $1,000 | Not Implemented |
HO0232 # 21 Y:2000 | 21 | 2000 | RECOVER AND REUSE WASTE MATERIAL | $93,600 | $500 | Not Implemented |
HO0232 # 08 Y:2000 | 08 | 2000 | OPTIMIZE PLANT POWER FACTOR | $2,647 | $4,134 | Not Implemented |
HO0232 # 12 Y:2000 | 12 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,400 | $1,035 | Not Implemented |
HO0232 # 09 Y:2000 | 09 | 2000 | IMPROVE SPACE COMFORT CONDITIONING | $18,360 | $8,000 | Not Implemented |
HO0232 # 11 Y:2000 | 11 | 2000 | IMPROVE SPACE COMFORT CONDITIONING | $11,520 | $724 | Not Implemented |