Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,274
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0369 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,038 | $0 | Implemented |
OK0369 # 04 Y:1992 | 04 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $946 | $0 | Implemented |
MO0048 # 04 Y:1992 | 04 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,183 | $292 | Implemented |
AM0135 # 01 Y:1991 | 01 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,330 | $6,532 | Implemented |
AM0135 # 02 Y:1991 | 02 | 1991 | INSULATE BARE EQUIPMENT | $2,190 | $100 | Implemented |
AM0135 # 03 Y:1991 | 03 | 1991 | INCREASE AMOUNT OF CONDENSATE RETURNED | $870 | $715 | Implemented |
AM0135 # 04 Y:1991 | 04 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $840 | $1,009 | Implemented |
AM0135 # 05 Y:1991 | 05 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $630 | $340 | Implemented |
AM0135 # 06 Y:1991 | 06 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $440 | $315 | Implemented |
AM0135 # 07 Y:1991 | 07 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $320 | $0 | Implemented |
AM0135 # 08 Y:1991 | 08 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $165 | $0 | Implemented |
AM0135 # 09 Y:1991 | 09 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $120 | $75 | Implemented |
UD0358 # 01 Y:1991 | 01 | 1991 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $10,464 | $7,000 | Implemented |
UD0358 # 02 Y:1991 | 02 | 1991 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $675 | $0 | Implemented |
UD0358 # 03 Y:1991 | 03 | 1991 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $2,145 | $200 | Implemented |
UD0358 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,170 | $0 | Implemented |
UD0358 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,636 | $0 | Implemented |
UD0358 # 06 Y:1991 | 06 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $959 | $0 | Implemented |
HO0008 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $631 | $1,032 | Implemented |
HO0008 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,973 | $742 | Implemented |
HO0008 # 03 Y:1991 | 03 | 1991 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,555 | $0 | Implemented |
HO0008 # 04 Y:1991 | 04 | 1991 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $235,098 | $0 | Implemented |
AS0040 # 01 Y:1991 | 01 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,811 | $2,794 | Implemented |
AS0040 # 02 Y:1991 | 02 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,154 | $0 | Implemented |
AS0040 # 03 Y:1991 | 03 | 1991 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,134 | $2,543 | Implemented |