Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,745
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0879 # 09 Y:2023 | 09 | 2023 | PAY UTILITY BILLS ON TIME | $275 | $0 | Not Implemented |
AM0879 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $485 | $200 | Not Implemented |
AM0879 # 07 Y:2023 | 07 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,765 | $4,340 | Not Implemented |
AM0879 # 06 Y:2023 | 06 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $1,995 | $257 | Not Implemented |
AM0879 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $955 | $0 | Not Implemented |
AM0879 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,790 | $825 | Not Implemented |
AM0879 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,050 | $8,145 | Not Implemented |
AM0879 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $5,195 | $11,085 | Not Implemented |
AM0879 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $30,265 | $6,430 | Not Implemented |
AM0878 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $140 | $160 | Not Implemented |
AM0878 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,590 | $1,900 | Not Implemented |
AM0878 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,735 | $14,637 | Not Implemented |
AM0878 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $16,950 | $39,180 | Not Implemented |
AM0875 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $1,130 | $460 | Implemented |
AM0875 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $925 | $500 | Implemented |
AM0875 # 06 Y:2023 | 06 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $965 | $15 | Implemented |
AM0875 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,920 | $15 | Implemented |
AM0875 # 04 Y:2023 | 04 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,630 | $4,160 | Implemented |
AM0875 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,370 | $900 | Not Implemented |
AM0875 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $22,785 | $7,000 | Implemented |
NT0002 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,414 | $5,801 | Implemented |
NT0002 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $14,389 | $21,853 | Not Implemented |
NT0002 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,026 | $2,499 | Implemented |
NT0002 # 04 Y:2023 | 04 | 2023 | INSTALL SET-BACK TIMERS | $1,504 | $0 | Implemented |
NT0002 # 05 Y:2023 | 05 | 2023 | ELIMINATE/REDUCE AN OPERATION | $9,631 | $0 | Implemented |