Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,436
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0121 # 05 Y:1995 | 05 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,118 | $1,583 | Implemented |
SD0121 # 06 Y:1995 | 06 | 1995 | ADD AREA LIGHTING SWITCHES | $1,489 | $800 | Not Implemented |
SD0121 # 07 Y:1995 | 07 | 1995 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $1,093 | $90 | Not Implemented |
SD0121 # 08 Y:1995 | 08 | 1995 | USE PHOTOCELL CONTROLS | $337 | $135 | Implemented |
SD0121 # 09 Y:1995 | 09 | 1995 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $6,480 | $0 | Implemented |
SD0121 # 10 Y:1995 | 10 | 1995 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,433 | $0 | Implemented |
SD0118 # 01 Y:1995 | 01 | 1995 | UPGRADE OBSOLETE EQUIPMENT | $8,154 | $15,000 | Implemented |
SD0118 # 02 Y:1995 | 02 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,560 | $20 | Implemented |
SD0118 # 03 Y:1995 | 03 | 1995 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $202 | $300 | Implemented |
SD0118 # 04 Y:1995 | 04 | 1995 | USE PHOTOCELL CONTROLS | $774 | $140 | Implemented |
SD0118 # 05 Y:1995 | 05 | 1995 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $578 | $100 | Implemented |
SD0118 # 06 Y:1995 | 06 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $6,794 | $1,430 | Implemented |
SD0118 # 07 Y:1995 | 07 | 1995 | BURN WOOD BY-PRODUCTS FOR HEAT | $9,000 | $5,000 | Not Implemented |
SD0118 # 08 Y:1995 | 08 | 1995 | IMPROVE CLEANING EFFICIENCY BY MAINTAINING CLEANING SYSTEM | $3,902 | $500 | Implemented |
SD0107 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,588 | $14,400 | Implemented |
SD0107 # 02 Y:1995 | 02 | 1995 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $94,795 | $22,000 | Implemented |
SD0107 # 03 Y:1995 | 03 | 1995 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,603 | $4,100 | Not Implemented |
SD0107 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,270 | $62,889 | Implemented |
SD0107 # 05 Y:1995 | 05 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $25,421 | $23,285 | Implemented |
SD0107 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $2,466 | $2,184 | Implemented |
SD0107 # 07 Y:1995 | 07 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,209 | $1,260 | Implemented |
SD0107 # 08 Y:1995 | 08 | 1995 | RECOVER AND REUSE COOLING WATER | $8,450 | $5,000 | Not Implemented |
SD0107 # 09 Y:1995 | 09 | 1995 | RECOVER AND REUSE COOLING WATER | $8,450 | $4,885 | Not Implemented |
SD0097 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $613 | $300 | Implemented |
SD0097 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $746 | $1,350 | Not Implemented |