Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,208
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0040 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,752 | $8,530 | Not Implemented |
HO0040 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,699 | $13,825 | Not Implemented |
HO0040 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $918 | $1,967 | Implemented |
HO0040 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,136 | $1,000 | Not Implemented |
HO0041 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,129 | $1,598 | Not Implemented |
HO0041 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $987 | $2,312 | Not Implemented |
HO0041 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,397 | $4,133 | Implemented |
HO0041 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,387 | $1,000 | Implemented |
HO0041 # 05 Y:1993 | 05 | 1993 | MOVE BOILER TO MORE EFFICIENT LOCATION | $1,899 | $200 | Not Implemented |
HO0041 # 06 Y:1993 | 06 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,508 | $0 | Implemented |
UF0060 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,244 | $46,210 | Not Implemented |
UF0060 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $719 | $2,833 | Not Implemented |
UF0060 # 03 Y:1993 | 03 | 1993 | INSTALL SPECTRAL REFLECTORS / DELAMP | $11,130 | $11,140 | Not Implemented |
UF0060 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $281 | $238 | Not Implemented |
UF0060 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,981 | $9,710 | Not Implemented |
UF0060 # 06 Y:1993 | 06 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,268 | $2,250 | Not Implemented |
UF0060 # 07 Y:1993 | 07 | 1993 | OPTIMIZE PLANT POWER FACTOR | $8,898 | $13,975 | Not Implemented |
UF0060 # 08 Y:1993 | 08 | 1993 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,618 | $3,700 | Not Implemented |
AS0079 # 01 Y:1993 | 01 | 1993 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $629 | $1,000 | Not Implemented |
AS0079 # 02 Y:1993 | 02 | 1993 | USE SYNTHETIC LUBRICANT | $228 | $0 | Not Implemented |
AS0079 # 03 Y:1993 | 03 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $926 | $400 | Not Implemented |
AS0079 # 04 Y:1993 | 04 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $157 | $208 | Not Implemented |
AS0079 # 05 Y:1993 | 05 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $359 | $0 | Not Implemented |
AS0079 # 06 Y:1993 | 06 | 1993 | USE HEAT PUMP FOR SPACE CONDITIONING | $357 | $1,420 | Not Implemented |
AS0079 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,526 | $5,661 | Not Implemented |