Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
436
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CC0030 # 08 Y:2023 | 08 | 2023 | INSULATE BARE EQUIPMENT | $219 | $868 | n/a |
CC0030 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $905 | $1,004 | n/a |
CC0030 # 07 Y:2023 | 07 | 2023 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $22,872 | $0 | n/a |
CC0030 # 05 Y:2023 | 05 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $64,875 | $571,150 | n/a |
CC0030 # 06 Y:2023 | 06 | 2023 | REPLACE BOILER | $7,589 | $100,666 | n/a |
CC0030 # 02 Y:2023 | 02 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13,211 | $9,178 | n/a |
CC0030 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $67,679 | $28,946 | n/a |
CC0030 # 04 Y:2023 | 04 | 2023 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $5,083 | $1,269 | n/a |
NC0656 # 04 Y:2021 | 04 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,212 | $111,000 | n/a |
NC0656 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,304 | $2,048 | n/a |
NC0656 # 02 Y:2021 | 02 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $39,666 | $500 | n/a |
NC0656 # 01 Y:2021 | 01 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $21,457 | $44,289 | n/a |
NC0619 # 10 Y:2018 | 10 | 2018 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $1,161 | $5,000 | Not Implemented |
NC0619 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $211 | $350 | Implemented |
NC0619 # 04 Y:2018 | 04 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,718 | $1,800 | Implemented |
NC0619 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,198 | $15,000 | Not Implemented |
NC0619 # 08 Y:2018 | 08 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $25,721 | $500 | Implemented |
NC0619 # 07 Y:2018 | 07 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,952 | $4,000 | Not Implemented |
NC0619 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,617 | $100 | Implemented |
NC0619 # 09 Y:2018 | 09 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $3,477 | $5,865 | Implemented |
NC0619 # 06 Y:2018 | 06 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,488 | $0 | Not Implemented |
NC0619 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,748 | $34,821 | Not Implemented |
NC0594 # 07 Y:2017 | 07 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,917 | $3,500 | Not Implemented |
NC0594 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,732 | $50 | Implemented |
NC0594 # 08 Y:2017 | 08 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,457 | $20,000 | Not Implemented |