Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2017 |
Principal Product | Heat exchangers |
NAICS | 332410 - Power Boiler and Heat Exchanger Manufacturing |
SIC | 3443 - Fabricated Plate Work (boiler Shops) |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 2,000,000 |
Annual Production | 200,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $401,701 | 9,232,919 | kWh | $0.04 |
Electricity Demand | $231,422 | 20,564 | kW-months/year | $11.25 |
Natural Gas | $68,039 | 13,845 | MMBtu | $4.91 |
TOTAL ENERGY COSTS | $701,162 | |||
RECOMMENDED SAVINGS* | $70,902 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $57,267 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $41,372 Cost: $77,272 |
$24,830 | 570,805 | $13,053 | 1,160 | - | - | - | - | $3,489 | - |
$24,830 570,805 kWh |
$13,053 1,160 kW-months/year |
- - MMBtu |
- - $ |
$3,489 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $5,666 Cost: $2,982 |
$5,666 | 130,254 | - | - | - | - | - | - | - | - |
$5,666 130,254 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,016 Cost: $8,200 |
$5,016 | 115,313 | - | - | - | - | - | - | - | - |
$5,016 115,313 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $2,502 Cost: $1,000 |
$2,502 | 69,316 | - | - | - | - | - | - | - | - |
$2,502 69,316 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $979 Cost: $100 |
$909 | 20,894 | $470 | 42 | - | - | $(-200) | - | $(-200) | - |
$909 20,894 kWh |
$470 42 kW-months/year |
- - MMBtu |
$(-200) - $ |
$(-200) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,732 Cost: $50 |
$1,142 | 26,244 | $590 | 52 | - | - | - | - | - | - |
$1,142 26,244 kWh |
$590 52 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,917 Cost: $3,500 |
- | - | - | - | $2,917 | 594 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,917 594 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,457 Cost: $20,000 |
- | - | - | - | $10,457 | 2,130 | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,457 2,130 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $261 Cost: $200 |
$261 | - | - | - | - | - | - | - | - | - |
$261 - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,902 Cost: $113,304 |
$40,326 | 932,826 | $14,113 | 1,254 | $13,374 | 2,724 | $(-200) | - | $3,289 | - | $40,326 932,826 kWh |
$14,113 1,254 kW-months/year |
$13,374 2,724 MMBtu |
$(-200) - $ |
$3,289 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $57,267 Cost: $89,604 |
$40,065 | 932,826 | $14,113 | 1,254 | - | - | $(-200) | - | $3,289 | - | $40,065 932,826 kWh |
$14,113 1,254 kW-months/year |
- - MMBtu |
$(-200) - $ |
$3,289 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |