Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

415

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0076 # 03 Y:2022 03 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,256 $4,500 Implemented
NL0076 # 05 Y:2022 05 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,194 $140 Implemented
NL0076 # 04 Y:2022 04 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,880 $12,650 Not Implemented
NL0076 # 02 Y:2022 02 2022 RECOVER WASTE HEAT FROM EQUIPMENT $24,481 $25,000 Not Implemented
NL0076 # 01 Y:2022 01 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $42,345 $20,000 Not Implemented
NL0076 # 07 Y:2022 07 2022 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,084 $35 Not Implemented
NL0076 # 06 Y:2022 06 2022 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $4,338 $7,210 Implemented
CI0006 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,588 $1,342 Not Implemented
CI0006 # 06 Y:2022 06 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,279 $500 Not Implemented
CI0006 # 05 Y:2022 05 2022 REPLACE BOILER $13,563 $27,000 Not Implemented
CI0006 # 04 Y:2022 04 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $14,859 $82,655 Not Implemented
CI0006 # 03 Y:2022 03 2022 RECOVER WASTE HEAT FROM EQUIPMENT $22,728 $6,000 Not Implemented
CI0006 # 02 Y:2022 02 2022 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $26,391 $90,000 Not Implemented
CI0006 # 01 Y:2022 01 2022 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $28,328 $32,800 Not Implemented
CI0005 # 10 Y:2022 10 2022 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $323 $0 Not Implemented
CI0005 # 02 Y:2022 02 2022 REPLACE BOILER $15,803 $9,000 Not Implemented
CI0005 # 03 Y:2022 03 2022 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $9,639 $30,000 Not Implemented
CI0005 # 04 Y:2022 04 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,840 $300 Not Implemented
CI0005 # 05 Y:2022 05 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $3,625 $13,372 Not Implemented
CI0005 # 09 Y:2022 09 2022 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $563 $500 Implemented
CI0005 # 08 Y:2022 08 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,446 $0 Not Implemented
CI0005 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,483 $99 Implemented
CI0005 # 06 Y:2022 06 2022 STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS $2,348 $8,100 Not Implemented
CI0005 # 01 Y:2022 01 2022 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $38,200 $16,400 Not Implemented
CO0746 # 03 Y:2022 03 2022 TURN OFF EQUIPMENT WHEN NOT IN USE $415 $0 n/a