Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
978
matching recommendationsSIC | 341 | Metal Cans And Shipping Containers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0298 # 10 Y:2004 | 10 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $794 | $1,825 | Not Implemented |
WV0298 # 09 Y:2004 | 09 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $736 | $705 | Implemented |
WV0298 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,304 | $0 | Implemented |
WV0298 # 07 Y:2004 | 07 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,877 | $240 | Implemented |
WV0298 # 06 Y:2004 | 06 | 2004 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,986 | $0 | Not Implemented |
WV0298 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $2,066 | $1,286 | Not Implemented |
WV0298 # 04 Y:2004 | 04 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,447 | $220 | Implemented |
WV0298 # 01 Y:2004 | 01 | 2004 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $3,459 | $2,100 | Not Implemented |
WV0298 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,929 | $440 | Implemented |
WV0298 # 03 Y:2004 | 03 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $2,864 | $1,928 | Not Implemented |
WV0298 # 13 Y:2004 | 13 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $461 | $360 | Implemented |
WV0298 # 12 Y:2004 | 12 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $565 | $1,000 | Not Implemented |
LE0184 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $35,446 | $0 | Not Implemented |
LE0184 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $34,434 | $10,000 | Implemented |
LE0184 # 03 Y:2004 | 03 | 2004 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $15,203 | $2,000 | Not Implemented |
LE0184 # 04 Y:2004 | 04 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $11,237 | $0 | Implemented |
LE0184 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,137 | $200 | Implemented |
LE0184 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,355 | $1,500 | Implemented |
LE0184 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,017 | $30,709 | Implemented |
WI0453 # 01 Y:2003 | 01 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $47,771 | $18,500 | Not Implemented |
WI0453 # 02 Y:2003 | 02 | 2003 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $22,445 | $40,000 | Not Implemented |
WI0453 # 03 Y:2003 | 03 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,041 | $18,315 | Implemented |
WI0453 # 04 Y:2003 | 04 | 2003 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $3,824 | $8,700 | Not Implemented |
WI0453 # 05 Y:2003 | 05 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,121 | $1,280 | Implemented |
WI0453 # 06 Y:2003 | 06 | 2003 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $4,657 | $20,000 | Not Implemented |