Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

35

matching recommendations
Reset
SIC 341 Metal Cans And Shipping Containers
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0518 # 02 Y:2022 02 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,190 $4,000 Implemented
LE0518 # 03 Y:2022 03 2022 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $6,790 $8,800 Implemented
LE0518 # 04 Y:2022 04 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,077 $30,000 Implemented
LE0518 # 05 Y:2022 05 2022 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $45,859 $175,000 Implemented
LE0518 # 06 Y:2022 06 2022 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $114,025 $450,000 Not Implemented
LE0518 # 01 Y:2022 01 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,198 $2,600 Implemented
LE0282 # 04 Y:2009 04 2009 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $9,314 $800 Not Implemented
LE0282 # 07 Y:2009 07 2009 INSTALL OCCUPANCY SENSORS $490 $450 Not Implemented
LE0282 # 06 Y:2009 06 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $18,538 $60,000 Implemented
LE0282 # 05 Y:2009 05 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,908 $3,000 Not Implemented
LE0282 # 03 Y:2009 03 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $19,083 $1,760 Implemented
LE0282 # 02 Y:2009 02 2009 CONVERT TO AIR ASSISTED / AIRLESS PAINT GUNS $20,433 $20,000 Implemented
LE0282 # 01 Y:2009 01 2009 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $45,837 $30,000 Not Implemented
HO0085 # 04 Y:1994 04 1994 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,316 $0 Not Implemented
HO0085 # 03 Y:1994 03 1994 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,113 $3,292 Not Implemented
HO0085 # 02 Y:1994 02 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $625 $1,454 Implemented
HO0085 # 01 Y:1994 01 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,495 $3,924 Implemented
RU0002 # 01 Y:1987 01 1987 IMPROVE LUBRICATION PRACTICES $22,514 $0 Implemented
RU0002 # 02 Y:1987 02 1987 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $30,280 $32,000 Implemented
RU0002 # 03 Y:1987 03 1987 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $8,433 $5,670 Implemented
RU0002 # 04 Y:1987 04 1987 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,800 $178 Implemented
RU0002 # 05 Y:1987 05 1987 INSULATE BARE EQUIPMENT $9,437 $6,204 Not Implemented
RU0002 # 06 Y:1987 06 1987 CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN $1,751 $0 Implemented
ST0049 # 01 Y:1985 01 1985 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,975 $500 Not Implemented
ST0049 # 02 Y:1985 02 1985 IMPROVE LUBRICATION PRACTICES $4,051 $0 Not Implemented