Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsSIC | 342 | Cutlery, Handtools, And Hardware |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0628 # 10 Y:2001 | 10 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $42,112 | $100,000 | Not Implemented |
OK0628 # 09 Y:2001 | 09 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $5,452 | $500 | Not Implemented |
OK0628 # 08 Y:2001 | 08 | 2001 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $456,570 | $93,000 | Not Implemented |
OK0628 # 07 Y:2001 | 07 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $20,767 | $5,653 | Not Implemented |
OK0628 # 06 Y:2001 | 06 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $75,988 | $752 | Implemented |
OK0628 # 05 Y:2001 | 05 | 2001 | INCREASE AMOUNT OF CONDENSATE RETURNED | $39,477 | $20,922 | Implemented |
OK0628 # 04 Y:2001 | 04 | 2001 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $2,448 | $1,500 | Implemented |
OK0628 # 03 Y:2001 | 03 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,940 | $3,013 | Implemented |
OK0628 # 02 Y:2001 | 02 | 2001 | INSTALL OCCUPANCY SENSORS | $357 | $613 | Implemented |
OK0628 # 01 Y:2001 | 01 | 2001 | INSTALL SET-BACK TIMERS | $8,150 | $310 | Implemented |
OR0404 # 04 Y:2001 | 04 | 2001 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $859 | $2,400 | Implemented |
OR0404 # 01 Y:2001 | 01 | 2001 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $25,650 | $0 | Implemented |
OR0404 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,457 | $1,102 | Implemented |
OR0404 # 06 Y:2001 | 06 | 2001 | OPTIMIZE PLANT POWER FACTOR | $250 | $700 | Not Implemented |
OR0403 # 02 Y:2001 | 02 | 2001 | INSTALL AUTOMATIC PACKING EQUIPMENT | $18,830 | $27,000 | Not Implemented |
OR0403 # 03 Y:2001 | 03 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,010 | $0 | Implemented |
OR0403 # 01 Y:2001 | 01 | 2001 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $20,460 | $860 | Implemented |
OR0403 # 04 Y:2001 | 04 | 2001 | ADD AREA LIGHTING SWITCHES | $645 | $1,400 | Not Implemented |
OR0404 # 03 Y:2001 | 03 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $546 | $1,065 | Implemented |
OR0404 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $448 | $500 | Implemented |
AS0308 # 08 Y:2001 | 08 | 2001 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $41,767 | $9,675 | n/a |
AS0308 # 06 Y:2001 | 06 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $660 | $106 | n/a |
AS0308 # 05 Y:2001 | 05 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $23,040 | $60 | n/a |
AS0308 # 04 Y:2001 | 04 | 2001 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $961 | $30 | n/a |
AS0308 # 03 Y:2001 | 03 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,163 | $4,543 | n/a |