Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
49
matching recommendationsSIC | 342 | Cutlery, Handtools, And Hardware |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0733 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $450 | $750 | n/a |
CO0733 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,360 | $5,950 | n/a |
CO0733 # 04 Y:2016 | 04 | 2016 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,970 | $34,800 | n/a |
CO0733 # 05 Y:2016 | 05 | 2016 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,200 | $500 | n/a |
CO0733 # 06 Y:2016 | 06 | 2016 | UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM | $2,200 | $9,200 | n/a |
CO0733 # 01 Y:2016 | 01 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,020 | $1,730 | n/a |
OK0949 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,319 | $5,020 | Not Implemented |
OK0949 # 02 Y:2016 | 02 | 2016 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,613 | $3,847 | Not Implemented |
OK0949 # 01 Y:2016 | 01 | 2016 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $17,826 | $50,400 | Not Implemented |
OK0949 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $720 | $1,313 | Not Implemented |
OK0949 # 05 Y:2016 | 05 | 2016 | OPERATE BOILERS ON HIGH FIRE SETTING | $10,228 | $44,000 | Not Implemented |
OK0949 # 07 Y:2016 | 07 | 2016 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $74,759 | $284,084 | Not Implemented |
OK0949 # 08 Y:2016 | 08 | 2016 | OPTIMIZE PLANT POWER FACTOR | $11,423 | $30,600 | Not Implemented |
OK0949 # 06 Y:2016 | 06 | 2016 | COVER OPEN TANKS | $9,702 | $850 | Not Implemented |
OK0948 # 01 Y:2016 | 01 | 2016 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,142 | $29,000 | Not Implemented |
OK0948 # 10 Y:2016 | 10 | 2016 | USE POWER DURING OFF-PEAK PERIODS | $12,184 | $0 | Not Implemented |
OK0948 # 05 Y:2016 | 05 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,007 | $926 | Not Implemented |
OK0948 # 04 Y:2016 | 04 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,857 | $18,014 | Not Implemented |
OK0948 # 03 Y:2016 | 03 | 2016 | USE PHOTOCELL CONTROLS | $862 | $3,870 | Not Implemented |
OK0948 # 07 Y:2016 | 07 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $45,797 | $118,583 | Not Implemented |
OK0948 # 09 Y:2016 | 09 | 2016 | USE OPTIMUM THICKNESS INSULATION | $58 | $203 | Implemented |
OK0948 # 08 Y:2016 | 08 | 2016 | USE OPTIMUM THICKNESS INSULATION | $382 | $1,310 | Implemented |
OK0948 # 06 Y:2016 | 06 | 2016 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $27,228 | $83,600 | Implemented |
OK0948 # 02 Y:2016 | 02 | 2016 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,510 | $2,320 | Implemented |
OK0948 # 11 Y:2016 | 11 | 2016 | OPTIMIZE PLANT POWER FACTOR | $7,251 | $25,830 | Implemented |