Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 3425 | Saw Blades And Handsaws |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0656 # 04 Y:2021 | 04 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,212 | $111,000 | n/a |
NC0656 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,304 | $2,048 | n/a |
NC0656 # 02 Y:2021 | 02 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $39,666 | $500 | n/a |
NC0656 # 01 Y:2021 | 01 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $21,457 | $44,289 | n/a |
UA0161 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $328 | $719 | Implemented |
UA0161 # 02 Y:2016 | 02 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $632 | $100 | Implemented |
UA0161 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,411 | $8,838 | Implemented |
UA0161 # 04 Y:2016 | 04 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $140 | $34 | Implemented |
NC0401 # 02 Y:2010 | 02 | 2010 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $7,833 | $0 | Implemented |
NC0401 # 07 Y:2010 | 07 | 2010 | INSTALL OCCUPANCY SENSORS | $5,761 | $3,750 | Implemented |
NC0401 # 06 Y:2010 | 06 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,947 | $6,200 | Implemented |
NC0401 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $845 | $200 | Implemented |
NC0401 # 04 Y:2010 | 04 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,940 | $7,800 | Implemented |
NC0401 # 01 Y:2010 | 01 | 2010 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $4,744 | $3,600 | Implemented |
NC0401 # 03 Y:2010 | 03 | 2010 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $5,578 | $0 | Implemented |
UF0372 # 01 Y:2005 | 01 | 2005 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $22,802 | $2,143 | Implemented |
UF0372 # 09 Y:2005 | 09 | 2005 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $43,072 | $138,308 | Not Implemented |
UF0372 # 08 Y:2005 | 08 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,724 | $39,583 | Not Implemented |
UF0372 # 07 Y:2005 | 07 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,223 | $16,223 | Implemented |
UF0372 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $55,681 | $32,374 | Not Implemented |
UF0372 # 05 Y:2005 | 05 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $10,158 | $28,067 | Not Implemented |
UF0372 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $3,070 | $1,427 | Not Implemented |
UF0372 # 03 Y:2005 | 03 | 2005 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,383 | $0 | Implemented |
UF0372 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,373 | $10,886 | Implemented |
UF0372 # 10 Y:2005 | 10 | 2005 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $26,386 | $121,152 | Not Implemented |