Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 3429 | Hardware, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0397 # 03 Y:2011 | 03 | 2011 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $239 | $10 | Implemented |
UM0397 # 02 Y:2011 | 02 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $13,335 | $30,200 | Not Implemented |
UM0397 # 01 Y:2011 | 01 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $5,033 | $200 | Implemented |
OK0814 # 05 Y:2011 | 05 | 2011 | ADJUST BURNERS FOR EFFICIENT OPERATION | $23,113 | $11,400 | Not Implemented |
OK0814 # 04 Y:2011 | 04 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,049 | $15,319 | Implemented |
OK0814 # 03 Y:2011 | 03 | 2011 | INSTALL EQUIPMENT TO MOVE PRODUCT | $1,364,602 | $235,960 | Implemented |
OK0814 # 02 Y:2011 | 02 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $189,220 | $20,000 | Implemented |
OK0814 # 01 Y:2011 | 01 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $262,832 | $1,710,000 | Implemented |
GT0882 # 09 Y:2011 | 09 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $47,117 | $155,150 | Implemented |
GT0882 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,634 | $0 | Implemented |
GT0882 # 08 Y:2011 | 08 | 2011 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $85,358 | $222,000 | Not Implemented |
GT0882 # 07 Y:2011 | 07 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $17,800 | $38,640 | Implemented |
GT0882 # 06 Y:2011 | 06 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $31,792 | $136,000 | Implemented |
GT0882 # 05 Y:2011 | 05 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $16,076 | $55,000 | Implemented |
GT0882 # 04 Y:2011 | 04 | 2011 | METER WASTE WATER | $3,614 | $6,000 | Not Implemented |
GT0882 # 03 Y:2011 | 03 | 2011 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $28,143 | $70,000 | Not Implemented |
GT0882 # 02 Y:2011 | 02 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,201 | $0 | Not Implemented |