Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
393
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0148 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,097 | $185 | Implemented |
IP0148 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $125 | $522 | Implemented |
IP0148 # 01 Y:2021 | 01 | 2021 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $104 | $0 | Not Implemented |
IP0148 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $126 | $504 | Not Implemented |
IP0148 # 02 Y:2021 | 02 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $844 | $0 | Implemented |
MZ0249 # 03 Y:2018 | 03 | 2018 | INSTALL OCCUPANCY SENSORS | $257 | $340 | Implemented |
MZ0249 # 01 Y:2018 | 01 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $607 | $1,750 | Implemented |
MZ0249 # 04 Y:2018 | 04 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $115 | $0 | Implemented |
MZ0249 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,399 | $0 | Implemented |
MZ0249 # 02 Y:2018 | 02 | 2018 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $10,248 | $15,240 | Implemented |
BD0476 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $791 | $490 | Not Implemented |
BD0476 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,120 | $700 | Not Implemented |
BD0476 # 01 Y:2016 | 01 | 2016 | IMPROVE COMBUSTION CONTROL CAPABILITY | $8,263 | $15,000 | Not Implemented |
BD0476 # 09 Y:2016 | 09 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $304 | $280 | Not Implemented |
BD0476 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $1,004 | $370 | Not Implemented |
BD0476 # 02 Y:2016 | 02 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,201 | $1,400 | Implemented |
BD0476 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $384 | $45 | Not Implemented |
BD0476 # 04 Y:2016 | 04 | 2016 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $4,708 | $3,000 | Not Implemented |
BD0476 # 10 Y:2016 | 10 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $228 | $700 | Not Implemented |
BD0476 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $629 | $300 | Not Implemented |
BD0475 # 04 Y:2016 | 04 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,266 | $4,390 | Implemented |
BD0475 # 03 Y:2016 | 03 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,287 | $9,000 | Not Implemented |
BD0475 # 14 Y:2016 | 14 | 2016 | CONVERT TO ELECTROSTATIC POWDER COATING | $28,428 | $90,000 | Not Implemented |
BD0475 # 01 Y:2016 | 01 | 2016 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $10,372 | $15,000 | Not Implemented |
BD0475 # 02 Y:2016 | 02 | 2016 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $6,954 | $18,000 | Not Implemented |