IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

291

matching recommendations
Reset
SIC 344 Fabricated Structural Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0474 # 02 Y:1995 02 1995 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $3,632 $3,553 Implemented
OK0474 # 01 Y:1995 01 1995 REPAIR AND ELIMINATE STEAM LEAKS $4,457 $4,457 Implemented
OK0471 # 02 Y:1995 02 1995 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,051 $80 Implemented
OK0471 # 01 Y:1995 01 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $609 $360 Implemented
OK0471 # 03 Y:1995 03 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,650 $6,490 Implemented
OK0471 # 05 Y:1995 05 1995 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $764 $410 Implemented
OK0471 # 06 Y:1995 06 1995 DISTILL CONTAMINATED SOLVENTS FOR REUSE $5,017 $5,994 Not Implemented
OK0471 # 04 Y:1995 04 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,762 $10,597 Implemented
OK0434 # 05 Y:1994 05 1994 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,881 $0 Not Implemented
OK0434 # 04 Y:1994 04 1994 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $6,960 $10,233 Not Implemented
OK0434 # 03 Y:1994 03 1994 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,859 $888 Not Implemented
OK0434 # 02 Y:1994 02 1994 RECOVER WASTE HEAT FROM EQUIPMENT $1,482 $1,440 Not Implemented
OK0434 # 01 Y:1994 01 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,860 $4,250 Implemented
OK0407 # 06 Y:1993 06 1993 INSTALL SET-BACK TIMERS $725 $750 Implemented
OK0407 # 05 Y:1993 05 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $971 $903 Implemented
OK0407 # 04 Y:1993 04 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,059 $0 Implemented
OK0407 # 03 Y:1993 03 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,186 $360 Not Implemented
OK0407 # 02 Y:1993 02 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,004 $0 Implemented
OK0407 # 01 Y:1993 01 1993 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $23,207 $118,871 Not Implemented
OK0389 # 05 Y:1992 05 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $262 $1,385 Implemented
OK0389 # 01 Y:1992 01 1992 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,084 $200 Implemented
OK0389 # 02 Y:1992 02 1992 KEEP LAMPS AND REFLECTORS CLEAN $2,686 $6,210 Not Implemented
OK0389 # 03 Y:1992 03 1992 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,437 $1,350 Implemented
OK0389 # 04 Y:1992 04 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $941 $1,348 Implemented
OK0389 # 07 Y:1992 07 1992 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $201 $683 Not Implemented