Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,509
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0486 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,397 | $51,976 | Implemented |
WV0486 # 01 Y:2014 | 01 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $27,561 | $100,000 | Not Implemented |
OK0874 # 01 Y:2014 | 01 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $380 | $112 | Implemented |
OK0874 # 02 Y:2014 | 02 | 2014 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $3,364 | $1,568 | Implemented |
OK0874 # 03 Y:2014 | 03 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,682 | $0 | Implemented |
OK0874 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,847 | $980 | Implemented |
OK0874 # 05 Y:2014 | 05 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,899 | $21,005 | Not Implemented |
OK0874 # 06 Y:2014 | 06 | 2014 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $934 | $1,024 | Implemented |
LE0370 # 01 Y:2014 | 01 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $3,349 | $0 | Implemented |
LE0370 # 02 Y:2014 | 02 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,947 | $35 | Implemented |
LE0370 # 03 Y:2014 | 03 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,490 | $200 | Implemented |
LE0370 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,076 | $1,000 | Implemented |
LE0370 # 05 Y:2014 | 05 | 2014 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $5,981 | $2,653 | Implemented |
LE0370 # 06 Y:2014 | 06 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,997 | $4,187 | Not Implemented |
LE0370 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,755 | $1,688 | Not Implemented |
LE0370 # 08 Y:2014 | 08 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,133 | $15,100 | Not Implemented |
LE0370 # 09 Y:2014 | 09 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,137 | $6,750 | Not Implemented |
LE0370 # 10 Y:2014 | 10 | 2014 | REPLACE BOILER | $61,996 | $205,000 | Not Implemented |
LE0370 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,070 | $75,880 | Not Implemented |
BD0435 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,612 | $12,980 | Implemented |
BD0435 # 02 Y:2013 | 02 | 2013 | USE PHOTOCELL CONTROLS | $1,708 | $500 | Not Implemented |
BD0435 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $654 | $730 | Implemented |
BD0435 # 04 Y:2013 | 04 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $618 | $2,100 | Not Implemented |
BD0435 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $287 | $250 | Not Implemented |
MZ0134 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $53,250 | $61,965 | Implemented |