Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
58
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0212 # 07 Y:1986 | 07 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,133 | $0 | Implemented |
OK0212 # 05 Y:1986 | 05 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,167 | $1,575 | Implemented |
OK0212 # 04 Y:1986 | 04 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,372 | $212 | Implemented |
OK0212 # 02 Y:1986 | 02 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,403 | $0 | Implemented |
OK0212 # 01 Y:1986 | 01 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,745 | $485 | Implemented |
OK0212 # 03 Y:1986 | 03 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $378 | $450 | Implemented |
OK0212 # 06 Y:1986 | 06 | 1986 | INSTALL SET-BACK TIMERS | $1,748 | $0 | Implemented |
AT0054 # 02 Y:1986 | 02 | 1986 | IMPROVE LUBRICATION PRACTICES | $4,453 | $0 | Implemented |
AT0054 # 08 Y:1986 | 08 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $122 | $150 | Implemented |
AT0054 # 07 Y:1986 | 07 | 1986 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $644 | $500 | Implemented |
AT0054 # 06 Y:1986 | 06 | 1986 | COVER OPEN TANKS | $7,949 | $1,850 | Implemented |
AT0054 # 05 Y:1986 | 05 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,521 | $0 | Implemented |
AT0054 # 04 Y:1986 | 04 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,066 | $150 | Implemented |
AT0054 # 03 Y:1986 | 03 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,134 | $0 | Implemented |
AT0054 # 09 Y:1986 | 09 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,814 | $1,500 | Implemented |
AT0054 # 01 Y:1986 | 01 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $820 | $986 | Implemented |
ST0068 # 07 Y:1986 | 07 | 1986 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $112,028 | $82,000 | Implemented |
ST0068 # 05 Y:1986 | 05 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,224 | $1,700 | Implemented |
ST0068 # 06 Y:1986 | 06 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,132 | $6,007 | Not Implemented |
ST0068 # 04 Y:1986 | 04 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $579 | $1,750 | Not Implemented |
ST0068 # 02 Y:1986 | 02 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $246 | $0 | Implemented |
ST0068 # 01 Y:1986 | 01 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,163 | $300 | Implemented |
ST0068 # 03 Y:1986 | 03 | 1986 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $264 | $1,000 | Implemented |
KU0201 # 04 Y:1986 | 04 | 1986 | IMPROVE LUBRICATION PRACTICES | $1,460 | $2,135 | Implemented |
KU0201 # 06 Y:1986 | 06 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,118 | $2,100 | Not Implemented |