IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

14

matching recommendations
Reset
SIC 3441 Fabricated Structural Metal
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0738 # 01 Y:2021 01 2021 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $242,489 $81,465 Not Implemented
OR0738 # 02 Y:2021 02 2021 OPTIMIZE PLANT POWER FACTOR $13,131 $8,725 Not Implemented
OR0738 # 03 Y:2021 03 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,831 $1,000 Not Implemented
OR0693 # 01 Y:2017 01 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,809 $500 Not Implemented
OR0693 # 02 Y:2017 02 2017 RECOVER WASTE HEAT FROM EQUIPMENT $5,614 $2,800 Not Implemented
OR0693 # 03 Y:2017 03 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $27,216 $28,216 Not Implemented
OR0693 # 04 Y:2017 04 2017 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $45,260 $144,180 Not Implemented
BS0096 # 01 Y:2017 01 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,641 $1,104 Implemented
BS0096 # 02 Y:2017 02 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $609 $175 Implemented
BS0096 # 03 Y:2017 03 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $355 $412 Implemented
BS0096 # 04 Y:2017 04 2017 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $152 $15 Not Implemented
BS0096 # 05 Y:2017 05 2017 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,155 $430 Not Implemented
BS0096 # 06 Y:2017 06 2017 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $1,509 $6,000 Implemented
BS0096 # 07 Y:2017 07 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $227 $564 Implemented