Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsSIC | 3448 | Prefabricated Metal Buildings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0227 # 07 Y:2001 | 07 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $24,960 | $30,230 | Implemented |
SF0227 # 06 Y:2001 | 06 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $807,300 | $190,000 | Implemented |
SF0227 # 05 Y:2001 | 05 | 2001 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,077 | $52 | Implemented |
SF0227 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $580 | $4,298 | Implemented |
SF0227 # 03 Y:2001 | 03 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $44,975 | $17,844 | Not Implemented |
SF0227 # 02 Y:2001 | 02 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,747 | $1,200 | Implemented |
SF0227 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,362 | $0 | Implemented |
BD0192 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $36,965 | $4,300 | Not Implemented |
BD0192 # 18 Y:2001 | 18 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $400 | $180 | Not Implemented |
BD0192 # 17 Y:2001 | 17 | 2001 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $598 | $250 | Not Implemented |
BD0192 # 16 Y:2001 | 16 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $4,091 | $3,600 | Not Implemented |
BD0192 # 15 Y:2001 | 15 | 2001 | RECOVER AND REUSE COOLING WATER | $4,930 | $12,000 | Not Implemented |
BD0192 # 14 Y:2001 | 14 | 2001 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $11,512 | $7,000 | n/a |
BD0192 # 12 Y:2001 | 12 | 2001 | CONVERT TO ELECTROSTATIC POWDER COATING | $420,915 | $581,000 | Not Implemented |
BD0192 # 01 Y:2001 | 01 | 2001 | USE RADIANT HEATER FOR SPOT HEATING | $276,125 | $40,500 | Not Implemented |
BD0192 # 03 Y:2001 | 03 | 2001 | DISCONNECT BALLASTS | $27,741 | $12,400 | n/a |
BD0192 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,184 | $51,960 | Not Implemented |
BD0192 # 05 Y:2001 | 05 | 2001 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $12,605 | $35,000 | Not Implemented |
BD0192 # 06 Y:2001 | 06 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,555 | $24,950 | Implemented |
BD0192 # 07 Y:2001 | 07 | 2001 | USE SYNTHETIC LUBRICANT | $9,075 | $5,000 | Not Implemented |
BD0192 # 08 Y:2001 | 08 | 2001 | INSTALL TURBULATORS | $8,641 | $1,500 | Not Implemented |
BD0192 # 13 Y:2001 | 13 | 2001 | CONVERT TO ELECTROSTATIC POWDER COATING | $168,710 | $9,250 | Not Implemented |
BD0192 # 11 Y:2001 | 11 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,513 | $690 | Not Implemented |
BD0192 # 10 Y:2001 | 10 | 2001 | INSTALL OCCUPANCY SENSORS | $2,689 | $2,700 | Implemented |
BD0192 # 09 Y:2001 | 09 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,939 | $5,000 | Not Implemented |