Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
397
matching recommendationsSIC | 3451 | Screw Machine Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0207 # 09 Y:1994 | 09 | 1994 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $408 | $0 | Not Implemented |
WI0207 # 10 Y:1994 | 10 | 1994 | RECYCLE CLEANING SOLVENT AND REUSE | $15,300 | $21,000 | Not Implemented |
WI0207 # 11 Y:1994 | 11 | 1994 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $7,000 | $10,000 | Not Implemented |
HO0071 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,097 | $8,138 | Implemented |
HO0071 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,235 | $7,710 | Implemented |
HO0071 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,010 | $1,953 | Implemented |
HO0071 # 04 Y:1994 | 04 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,626 | $495 | Implemented |
AS0088 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $775 | $1,485 | Implemented |
AS0088 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $243 | $420 | Implemented |
AS0088 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $900 | $1,166 | Not Implemented |
AS0088 # 04 Y:1993 | 04 | 1993 | INSTALL OCCUPANCY SENSORS | $191 | $375 | Not Implemented |
AS0088 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $160 | $136 | Implemented |
AS0088 # 06 Y:1993 | 06 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $191 | $260 | Not Implemented |
AS0088 # 07 Y:1993 | 07 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,290 | $650 | Implemented |
AS0088 # 08 Y:1993 | 08 | 1993 | USE SYNTHETIC LUBRICANT | $2,626 | $4,776 | Implemented |
AS0088 # 09 Y:1993 | 09 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $628 | $1,380 | Implemented |
AS0088 # 10 Y:1993 | 10 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,254 | $0 | Implemented |
AS0088 # 11 Y:1993 | 11 | 1993 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $704 | $2,450 | Not Implemented |
AS0088 # 12 Y:1993 | 12 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $1,022 | $1,120 | Implemented |
WI0174 # 06 Y:1993 | 06 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,100 | $1,559 | Not Implemented |
WI0174 # 01 Y:1993 | 01 | 1993 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,356 | $6,000 | Not Implemented |
WI0174 # 02 Y:1993 | 02 | 1993 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $1,898 | $0 | Implemented |
WI0174 # 03 Y:1993 | 03 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,038 | $600 | Not Implemented |
WI0174 # 04 Y:1993 | 04 | 1993 | INSTALL OCCUPANCY SENSORS | $1,642 | $1,000 | Not Implemented |
WI0174 # 09 Y:1993 | 09 | 1993 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $787 | $500 | Not Implemented |