matching recommendationsSIC | 3451 | Screw Machine Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0380 # 14 Y:2008 | 14 | 2008 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $807 | $4,400 | Not Implemented |
WV0380 # 13 Y:2008 | 13 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,422 | $225 | Not Implemented |
WV0380 # 12 Y:2008 | 12 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,891 | $0 | Implemented |
WV0380 # 11 Y:2008 | 11 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,989 | $1,550 | Implemented |
WV0380 # 10 Y:2008 | 10 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,058 | $30 | Implemented |
WV0380 # 09 Y:2008 | 09 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $2,626 | $1,018 | Implemented |
WV0380 # 08 Y:2008 | 08 | 2008 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,853 | $13,200 | Not Implemented |
WV0380 # 07 Y:2008 | 07 | 2008 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,939 | $1,690 | Implemented |
WV0380 # 06 Y:2008 | 06 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,106 | $1,120 | Not Implemented |
WV0380 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,310 | $0 | Implemented |
WV0380 # 04 Y:2008 | 04 | 2008 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $6,055 | $4,950 | Not Implemented |
WV0380 # 03 Y:2008 | 03 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,429 | $3,300 | Not Implemented |
WV0380 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,037 | $8,850 | Implemented |
WV0380 # 01 Y:2008 | 01 | 2008 | OPTIMIZE PLANT POWER FACTOR | $18,045 | $7,420 | Not Implemented |
LE0275 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,646 | $6,020 | Implemented |
LE0275 # 11 Y:2008 | 11 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,143 | $47,522 | Not Implemented |
LE0275 # 10 Y:2008 | 10 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,664 | $50 | Implemented |
LE0275 # 09 Y:2008 | 09 | 2008 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,949 | $4,000 | Not Implemented |
LE0275 # 08 Y:2008 | 08 | 2008 | INSTALL OCCUPANCY SENSORS | $5,121 | $300 | Implemented |
LE0275 # 07 Y:2008 | 07 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,495 | $11,500 | Not Implemented |
LE0275 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,675 | $1,000 | Implemented |
LE0275 # 05 Y:2008 | 05 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,781 | $2,200 | Not Implemented |
LE0275 # 04 Y:2008 | 04 | 2008 | USE RADIANT HEATER FOR SPOT HEATING | $9,912 | $5,250 | Not Implemented |
LE0275 # 03 Y:2008 | 03 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,225 | $1,800 | Implemented |
LE0275 # 01 Y:2008 | 01 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $22,241 | $20,000 | Not Implemented |