Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
656
matching recommendationsSIC | 3452 | Bolts, Nuts, Rivets, And Washers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0353 # 13 Y:1999 | 13 | 1999 | INSTALL SKYLIGHTS | $300 | $1,400 | Implemented |
AM0353 # 14 Y:1999 | 14 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $240 | $250 | Implemented |
AR0147 # 01 Y:1998 | 01 | 1998 | INSULATE BARE EQUIPMENT | $1,129 | $464 | Not Implemented |
AR0147 # 02 Y:1998 | 02 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $645 | $60 | Not Implemented |
AR0147 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $986 | $160 | Not Implemented |
AR0147 # 04 Y:1998 | 04 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,700 | $0 | Not Implemented |
AR0147 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,406 | $8,100 | Not Implemented |
AR0147 # 06 Y:1998 | 06 | 1998 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $2,387 | $0 | Not Implemented |
AR0147 # 07 Y:1998 | 07 | 1998 | RECYCLE WHITE WATER | $5,032 | $0 | Not Implemented |
AR0147 # 08 Y:1998 | 08 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $26,479 | $19,950 | Not Implemented |
UD0552 # 01 Y:1998 | 01 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $199,687 | $0 | Not Implemented |
UD0552 # 02 Y:1998 | 02 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $9,000 | $12,000 | Not Implemented |
UD0552 # 03 Y:1998 | 03 | 1998 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $18,478 | $1,800 | Not Implemented |
UD0552 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,681 | $7,118 | Not Implemented |
UD0552 # 05 Y:1998 | 05 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,972 | $0 | Not Implemented |
UD0552 # 06 Y:1998 | 06 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,132 | $600 | Implemented |
UD0552 # 07 Y:1998 | 07 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,486 | $2,000 | Implemented |
WI0317 # 01 Y:1998 | 01 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,682 | $1,342 | Not Implemented |
WI0317 # 02 Y:1998 | 02 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $986 | $0 | Not Implemented |
WI0317 # 03 Y:1998 | 03 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $597 | $2,250 | Not Implemented |
WI0317 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,138 | $740 | Not Implemented |
WI0317 # 07 Y:1998 | 07 | 1998 | REPLACE CLOTH RAGS WITH PAPER TOWELS | $400 | $0 | Not Implemented |
WI0317 # 06 Y:1998 | 06 | 1998 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $794 | $0 | Implemented |
WI0317 # 04 Y:1998 | 04 | 1998 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $1,611 | $0 | Implemented |
UM0090 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,096 | $1,755 | Implemented |