IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,137

matching recommendations
Reset
SIC 346 Metal Forgings And Stampings
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0107 # 08 Y:1991 08 1991 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,042 $5,000 Implemented
UD0327 # 01 Y:1990 01 1990 OPTIMIZE PLANT POWER FACTOR $14,606 $12,000 Implemented
UD0327 # 02 Y:1990 02 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $49,772 $3,000 Implemented
UD0327 # 04 Y:1990 04 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $-1,479 $540 Implemented
RU0092 # 01 Y:1990 01 1990 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $261 $34 Implemented
RU0092 # 02 Y:1990 02 1990 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,505 $500 Implemented
RU0092 # 03 Y:1990 03 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,267 $214 Implemented
RU0092 # 06 Y:1990 06 1990 USE OPTIMUM THICKNESS INSULATION $9,910 $80,000 Implemented
KU0313 # 02 Y:1990 02 1990 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $11,447 $20,000 Implemented
KU0313 # 03 Y:1990 03 1990 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,866 $80 Implemented
KU0313 # 04 Y:1990 04 1990 INSTALL TIMERS AND/OR THERMOSTATS $620 $100 Implemented
MA0172 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $499 $168 Implemented
MA0172 # 02 Y:1990 02 1990 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $4,911 $2,000 Implemented
MA0172 # 03 Y:1990 03 1990 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,721 $326 Implemented
WI0066 # 03 Y:1989 03 1989 INSTALL TIMERS AND/OR THERMOSTATS $2,703 $750 Implemented
WI0066 # 05 Y:1989 05 1989 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $2,710 $0 Implemented
WI0066 # 06 Y:1989 06 1989 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,350 $450 Implemented
WI0066 # 08 Y:1989 08 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $573 $3,346 Implemented
WI0066 # 10 Y:1989 10 1989 INSTALL SET-BACK TIMERS $481 $400 Implemented
WI0066 # 11 Y:1989 11 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $197 $500 Implemented
UD0299 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $900 $0 Implemented
UD0299 # 03 Y:1989 03 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,667 $750 Implemented
UD0299 # 04 Y:1989 04 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $889 $750 Implemented
UD0299 # 05 Y:1989 05 1989 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $1,588 $1,720 Implemented
OK0285 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,402 $3,870 Implemented