Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 346 | Metal Forgings And Stampings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0640 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,135 | $10,165 | Implemented |
WV0640 # 12 Y:2023 | 12 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $66 | $178 | Implemented |
WV0640 # 10 Y:2023 | 10 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,582 | $5,558 | Implemented |
WV0640 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,011 | $596 | Implemented |
WV0640 # 07 Y:2023 | 07 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $3,201 | $1,563 | Implemented |
WV0640 # 06 Y:2023 | 06 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,905 | $1,500 | Implemented |
WV0640 # 11 Y:2023 | 11 | 2023 | INSULATE BARE EQUIPMENT | $930 | $135 | Implemented |
WV0640 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,002 | $9,194 | Implemented |
LE0537 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $57,920 | $245,000 | Implemented |
LE0537 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,096 | $67,533 | Implemented |
LE0537 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $825 | $570 | Implemented |
LE0537 # 01 Y:2023 | 01 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $167,234 | $0 | Implemented |
LE0509 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,834 | $2,500 | Implemented |
LE0509 # 03 Y:2021 | 03 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,755 | $56,400 | Implemented |
LE0509 # 04 Y:2021 | 04 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,037 | $8,000 | Implemented |
LE0509 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,633 | $9,000 | Implemented |
WV0584 # 06 Y:2019 | 06 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $7,129 | $675 | Implemented |
WV0584 # 10 Y:2019 | 10 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,028 | $5,443 | Implemented |
WV0584 # 11 Y:2019 | 11 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $876 | $358 | Implemented |
WV0584 # 03 Y:2019 | 03 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $44,593 | $129,500 | Implemented |
WV0584 # 09 Y:2019 | 09 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,899 | $510 | Implemented |
WV0584 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $18,530 | $6,283 | Implemented |
WV0584 # 07 Y:2019 | 07 | 2019 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $5,503 | $1,000 | Implemented |
LE0468 # 06 Y:2019 | 06 | 2019 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $726,896 | $16,000,000 | Implemented |
LE0468 # 05 Y:2019 | 05 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,988 | $50,000 | Implemented |