Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 346 | Metal Forgings And Stampings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0225 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,274 | $4,150 | Implemented |
IC0225 # 03 Y:2019 | 03 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,600 | $105 | Not Implemented |
IC0225 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,947 | $3,110 | Implemented |
IC0225 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,711 | $3,850 | Not Implemented |
IC0225 # 06 Y:2019 | 06 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $2,596 | $652 | Implemented |
IC0225 # 07 Y:2019 | 07 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $10,365 | $18,280 | Not Implemented |
IC0225 # 01 Y:2019 | 01 | 2019 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $44,444 | $23,100 | Implemented |
MI0362 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,851 | $160 | Not Implemented |
MI0362 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,814 | $1,980 | Implemented |
MI0362 # 05 Y:2019 | 05 | 2019 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $2,811 | $1,120 | Not Implemented |
MI0362 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,441 | $3,600 | Implemented |
MI0362 # 02 Y:2019 | 02 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $49,454 | $216,900 | Not Implemented |
MI0362 # 09 Y:2019 | 09 | 2019 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,147 | $1,090 | Implemented |
MI0362 # 07 Y:2019 | 07 | 2019 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $1,481 | $185 | Implemented |
MI0362 # 08 Y:2019 | 08 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,148 | $1,126 | Implemented |
MI0362 # 01 Y:2019 | 01 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $67,585 | $640 | Not Implemented |
MI0362 # 10 Y:2019 | 10 | 2019 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $288 | $187 | Implemented |
WV0584 # 09 Y:2019 | 09 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,899 | $510 | Implemented |
WV0584 # 08 Y:2019 | 08 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $5,427 | $8,500 | Not Implemented |
WV0584 # 06 Y:2019 | 06 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $7,129 | $675 | Implemented |
WV0584 # 11 Y:2019 | 11 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $876 | $358 | Implemented |
WV0584 # 10 Y:2019 | 10 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,028 | $5,443 | Implemented |
WV0584 # 04 Y:2019 | 04 | 2019 | RECYCLE WHITE WATER | $26,110 | $17,500 | Not Implemented |
WV0584 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $18,530 | $6,283 | Implemented |
WV0584 # 01 Y:2019 | 01 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $534,947 | $542,300 | Not Implemented |