Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
164
matching recommendationsSIC | 3463 | Nonferrous Forgings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0538 # 01 Y:1995 | 01 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,201 | $0 | Implemented |
TN0538 # 02 Y:1995 | 02 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,149 | $0 | Not Implemented |
TN0538 # 03 Y:1995 | 03 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,115 | $253 | Implemented |
TN0538 # 04 Y:1995 | 04 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $471 | $810 | Not Implemented |
TN0538 # 05 Y:1995 | 05 | 1995 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $218 | $435 | Not Implemented |
TN0538 # 06 Y:1995 | 06 | 1995 | OPTIMIZE PLANT POWER FACTOR | $4,892 | $5,000 | Implemented |
UD0327 # 01 Y:1990 | 01 | 1990 | OPTIMIZE PLANT POWER FACTOR | $14,606 | $12,000 | Implemented |
UD0327 # 02 Y:1990 | 02 | 1990 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $49,772 | $3,000 | Implemented |
UD0327 # 03 Y:1990 | 03 | 1990 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $1,063 | $1,000 | Not Implemented |
UD0327 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $-1,479 | $540 | Implemented |
UD0327 # 05 Y:1990 | 05 | 1990 | INSTALL TIMERS AND/OR THERMOSTATS | $962 | $600 | Not Implemented |
MA0172 # 01 Y:1990 | 01 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $499 | $168 | Implemented |
MA0172 # 02 Y:1990 | 02 | 1990 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $4,911 | $2,000 | Implemented |
MA0172 # 03 Y:1990 | 03 | 1990 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,721 | $326 | Implemented |