Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
178
matching recommendationsSIC | 347 | Metal Services, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0118 # 07 Y:2006 | 07 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,403 | $2,544 | Implemented |
IC0118 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $953 | $1,200 | Implemented |
IC0118 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $428 | $516 | Implemented |
IC0118 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $235 | $1,132 | Implemented |
IC0118 # 11 Y:2006 | 11 | 2006 | INSTALL OCCUPANCY SENSORS | $62 | $291 | Not Implemented |
IC0095 # 01 Y:2005 | 01 | 2005 | USE IMMERSION HEATING IN TANKS, MELTING POTS, ETC | $30,106 | $55,000 | Not Implemented |
IC0095 # 02 Y:2005 | 02 | 2005 | MOVE BOILER TO MORE EFFICIENT LOCATION | $47,879 | $205,000 | Not Implemented |
IC0095 # 03 Y:2005 | 03 | 2005 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $116,731 | $400,000 | Not Implemented |
IC0095 # 04 Y:2005 | 04 | 2005 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $16,405 | $50,000 | Not Implemented |
IC0095 # 05 Y:2005 | 05 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,441 | $0 | Implemented |
IC0095 # 06 Y:2005 | 06 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,852 | $9,142 | Implemented |
IC0095 # 07 Y:2005 | 07 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $1,812 | $2,700 | Implemented |
IC0095 # 08 Y:2005 | 08 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $716 | $992 | Implemented |
IC0095 # 09 Y:2005 | 09 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,010 | $3,168 | Not Implemented |
IC0095 # 10 Y:2005 | 10 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,367 | $1,200 | Implemented |
IC0095 # 11 Y:2005 | 11 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,515 | $0 | Implemented |
IC0095 # 12 Y:2005 | 12 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,034 | $1,400 | Not Implemented |
IC0095 # 13 Y:2005 | 13 | 2005 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $5,283 | $24,720 | Not Implemented |
IC0037 # 01 Y:2002 | 01 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $873 | $3,949 | Not Implemented |
IC0037 # 02 Y:2002 | 02 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $472 | $440 | Implemented |
IC0026 # 01 Y:2002 | 01 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $945 | $8,326 | Implemented |
IC0026 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,379 | $25,075 | Not Implemented |
IC0026 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $102 | $150 | Implemented |
IC0026 # 04 Y:2002 | 04 | 2002 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $205,600 | $100,000 | Not Implemented |
IC0026 # 05 Y:2002 | 05 | 2002 | MODIFY WORKLOAD | $77,900 | $23,900 | Implemented |