Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2008 |
Principal Product | Metal PLating |
NAICS | 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 96,000 |
Annual Production | 8,500,000 Pounds |
Production Hrs. Annual | 4,208 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $33,047 | 468,173 | kWh | $0.07 |
Electricity Demand | $7,995 | 1,264 | kW-months/year | $6.33 |
Natural Gas | $10,489 | 1,101 | MMBtu | $9.53 |
TOTAL ENERGY COSTS | $90,597 | |||
RECOMMENDED SAVINGS* | $28,863 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,851 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $261 Cost: $300 |
$72 | 1,016 | $6 | 1 | - | - | - | - | $56 | - | $127 | - |
$72 1,016 kWh |
$6 1 kW-months/year |
- - MMBtu |
- - Tgal |
$56 - $ |
$127 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $156 Cost: $102 |
$90 | 1,262 | $25 | 4 | - | - | - | - | $43 | - | $(-2) | - |
$90 1,262 kWh |
$25 4 kW-months/year |
- - MMBtu |
- - Tgal |
$43 - $ |
$(-2) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,624 Cost: $2,693 |
$1,290 | 18,178 | $334 | 53 | - | - | - | - | - | - | - | - |
$1,290 18,178 kWh |
$334 53 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $476 Cost: $1,278 |
$381 | 5,376 | $95 | 15 | - | - | - | - | - | - | - | - |
$381 5,376 kWh |
$95 15 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $55 Cost: - |
$36 | 506 | $19 | 3 | - | - | - | - | - | - | - | - |
$36 506 kWh |
$19 3 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,124 Cost: $913 |
$896 | 12,624 | $228 | 36 | - | - | - | - | - | - | - | - |
$896 12,624 kWh |
$228 36 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $4,155 Cost: - |
- | - | - | - | $4,155 | 436 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,155 436 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4113 TREAT AND REUSE RINSE WATERS |
Savings: $21,012 Cost: $27,696 |
- | - | - | - | - | - | $21,012 | 3,420,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$21,012 3,420,000 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,863 Cost: $32,982 |
$2,765 | 38,962 | $707 | 112 | $4,155 | 436 | $21,012 | 3,420,000 | $99 | - | $125 | - | $2,765 38,962 kWh |
$707 112 kW-months/year |
$4,155 436 MMBtu |
$21,012 3,420,000 Tgal |
$99 - $ |
$125 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,851 Cost: $5,286 |
$2,765 | 38,962 | $707 | 112 | $4,155 | 436 | - | - | $99 | - | $125 | - | $2,765 38,962 kWh |
$707 112 kW-months/year |
$4,155 436 MMBtu |
- - Tgal |
$99 - $ |
$125 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost |