Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
90
matching recommendationsSIC | 349 | Misc. Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0267 # 01 Y:2005 | 01 | 2005 | OPTIMIZE PLANT POWER FACTOR | $30,643 | $45,270 | Implemented |
MS0267 # 05 Y:2005 | 05 | 2005 | AIR CONDITION ONLY SPACE NECESSARY | $613 | $240 | Not Implemented |
MS0267 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $750 | $228 | Implemented |
MS0267 # 06 Y:2005 | 06 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $128 | $0 | Not Implemented |
MS0267 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,354 | $141,305 | Implemented |
MS0265 # 04 Y:2004 | 04 | 2004 | BURN WASTE OIL FOR HEAT | $3,362 | $3,129 | Not Implemented |
MS0265 # 06 Y:2004 | 06 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $791 | $472 | Not Implemented |
MS0265 # 07 Y:2004 | 07 | 2004 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $774 | $176 | Not Implemented |
MS0265 # 03 Y:2004 | 03 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $5,480 | $2,430 | Not Implemented |
MS0265 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,680 | $189 | Implemented |
MS0265 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,523 | $32,157 | Not Implemented |
MS0265 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36,775 | $59,467 | Implemented |
MS0264 # 04 Y:2004 | 04 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,356 | $1,624 | Not Implemented |
MS0264 # 03 Y:2004 | 03 | 2004 | AIR CONDITION ONLY SPACE NECESSARY | $2,457 | $480 | Not Implemented |
MS0264 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,737 | $318 | Implemented |
MS0264 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,471 | $84,783 | Implemented |
MS0264 # 06 Y:2004 | 06 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $183 | $249 | Not Implemented |
MS0264 # 05 Y:2004 | 05 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $989 | $944 | Not Implemented |
MS0202 # 01 Y:2002 | 01 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $8,051 | $5,798 | Not Implemented |
MS0202 # 02 Y:2002 | 02 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,165 | $2,954 | Implemented |
MS0202 # 03 Y:2002 | 03 | 2002 | USE RADIANT HEATER FOR SPOT HEATING | $5,910 | $800 | Implemented |
MS0202 # 04 Y:2002 | 04 | 2002 | INSTALL TIMERS AND/OR THERMOSTATS | $1,270 | $100 | Implemented |
MS0202 # 05 Y:2002 | 05 | 2002 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $571 | $173 | Implemented |
MS0202 # 06 Y:2002 | 06 | 2002 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $4,800 | $0 | Implemented |
MS0192 # 05 Y:2001 | 05 | 2001 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $1,153 | $3,127 | Implemented |