Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 349 | Misc. Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0751 # 04 Y:2022 | 04 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,125 | $1,272 | Not Implemented |
OR0751 # 03 Y:2022 | 03 | 2022 | FILTER AND REUSE HYDRAULIC OIL | $74,774 | $48,589 | Not Implemented |
OR0751 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,956 | $1,175 | Not Implemented |
OR0751 # 01 Y:2022 | 01 | 2022 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $12,526 | $140 | Not Implemented |
OR0295 # 04 Y:1997 | 04 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $940 | $500 | Not Implemented |
OR0295 # 08 Y:1997 | 08 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $775 | $2,723 | Implemented |
OR0295 # 07 Y:1997 | 07 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,116 | $6,360 | Implemented |
OR0295 # 06 Y:1997 | 06 | 1997 | COVER OPEN TANKS | $1,160 | $1,360 | Not Implemented |
OR0295 # 05 Y:1997 | 05 | 1997 | BURN A LESS EXPENSIVE GRADE OF FUEL | $7,820 | $10,000 | Not Implemented |
OR0295 # 03 Y:1997 | 03 | 1997 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,830 | $890 | Not Implemented |
OR0295 # 02 Y:1997 | 02 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $36,000 | $40,000 | Not Implemented |
OR0295 # 01 Y:1997 | 01 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $86,250 | $1,000 | Not Implemented |
OR0087 # 01 Y:1990 | 01 | 1990 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,019 | $548 | Not Implemented |
OR0087 # 05 Y:1990 | 05 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $250 | $744 | Implemented |
OR0087 # 04 Y:1990 | 04 | 1990 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $38,901 | $50,000 | Implemented |
OR0087 # 03 Y:1990 | 03 | 1990 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $95 | $0 | Implemented |
OR0087 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $934 | $1,451 | Implemented |