IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

99

matching recommendations
Reset
SIC 349 Misc. Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0068 # 03 Y:1989 03 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,616 $7,000 Not Implemented
WI0070 # 03 Y:1989 03 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $4,871 $2,400 Not Implemented
WI0070 # 04 Y:1989 04 1989 INSTALL TIMERS AND/OR THERMOSTATS $3,122 $250 Not Implemented
WI0070 # 02 Y:1989 02 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $16,961 $0 Implemented
WI0068 # 02 Y:1989 02 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,780 $5,000 Implemented
WI0068 # 06 Y:1989 06 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $1,052 $0 Not Implemented
WI0070 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $27,544 $28,341 Implemented
WI0068 # 04 Y:1989 04 1989 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $1,353 $0 Implemented
WI0070 # 05 Y:1989 05 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,255 $1,000 Not Implemented
WI0068 # 01 Y:1989 01 1989 INSTALL TIMERS AND/OR THERMOSTATS $5,126 $1,300 Not Implemented
WI0068 # 05 Y:1989 05 1989 IMPROVE LUBRICATION PRACTICES $1,174 $0 Not Implemented
WI0068 # 07 Y:1989 07 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $600 $1,000 Implemented
WI0070 # 06 Y:1989 06 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $409 $0 Implemented
RU0070 # 01 Y:1989 01 1989 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $21,495 $51,000 Not Implemented
OK0296 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,120 $5,685 Implemented
OK0296 # 02 Y:1989 02 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $771 $1,425 Implemented
RU0070 # 02 Y:1989 02 1989 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,082 $0 Not Implemented
OK0296 # 03 Y:1989 03 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $156 $0 Implemented
OK0296 # 04 Y:1989 04 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $180 $155 Implemented
OK0296 # 05 Y:1989 05 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $542 $1,336 Implemented
OK0296 # 06 Y:1989 06 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $494 $0 Implemented
RU0070 # 05 Y:1989 05 1989 RECOVER WASTE HEAT FROM EQUIPMENT $12,730 $3,000 Implemented
RU0070 # 04 Y:1989 04 1989 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $16,973 $56,000 Not Implemented
RU0070 # 03 Y:1989 03 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $971 $332 Implemented
UD0300 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,322 $0 Not Implemented