Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
462
matching recommendationsSIC | 3491 | Industrial Valves |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0164 # 05 Y:1999 | 05 | 1999 | INSULATE BARE EQUIPMENT | $486 | $160 | Not Implemented |
WV0164 # 06 Y:1999 | 06 | 1999 | OPTIMIZE PLANT POWER FACTOR | $2,790 | $8,810 | Not Implemented |
WV0164 # 07 Y:1999 | 07 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $918 | $428 | Implemented |
WV0164 # 08 Y:1999 | 08 | 1999 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $523 | $192 | Implemented |
WV0164 # 09 Y:1999 | 09 | 1999 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $1,200 | $1,584 | Implemented |
WV0164 # 10 Y:1999 | 10 | 1999 | CLEAR AND RENT EXISTING SPACE | $7,200 | $1,920 | Implemented |
MA0437 # 01 Y:1999 | 01 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,316 | $3,000 | Not Implemented |
MA0437 # 02 Y:1999 | 02 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,292 | $1,892 | Not Implemented |
MA0437 # 03 Y:1999 | 03 | 1999 | UPGRADE CONTROLS ON COMPRESSORS | $6,214 | $400 | Implemented |
MA0437 # 04 Y:1999 | 04 | 1999 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $2,225 | $300 | Implemented |
MA0437 # 05 Y:1999 | 05 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,451 | $2,445 | Implemented |
MA0437 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $774 | $0 | Implemented |
AR0151 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,881 | $200 | Not Implemented |
AR0151 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $602 | $400 | Not Implemented |
AR0151 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,208 | $17,401 | Not Implemented |
AR0151 # 04 Y:1998 | 04 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $413 | $1,107 | Not Implemented |
AR0151 # 05 Y:1998 | 05 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $716 | $0 | Not Implemented |
AR0151 # 06 Y:1998 | 06 | 1998 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $2,894 | $6,000 | Not Implemented |
AR0151 # 07 Y:1998 | 07 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $11,422 | $2,500 | Not Implemented |
AR0148 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,477 | $500 | Implemented |
AR0148 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $637 | $1,060 | Not Implemented |
AR0148 # 03 Y:1998 | 03 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,475 | $0 | Not Implemented |
AR0148 # 04 Y:1998 | 04 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,792 | $850 | Not Implemented |
AR0148 # 05 Y:1998 | 05 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $40,673 | $1,200 | Implemented |
AR0148 # 06 Y:1998 | 06 | 1998 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $39,295 | $91,825 | Implemented |