IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

547

matching recommendations
Reset
SIC 3494 Valves And Pipe Fittings, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0629 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,176 $879 Not Implemented
AM0629 # 05 Y:2013 05 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $7,548 $300 Not Implemented
AM0629 # 04 Y:2013 04 2013 USE PHOTOCELL CONTROLS $9,077 $1,574 Not Implemented
AM0629 # 03 Y:2013 03 2013 INSTALL OCCUPANCY SENSORS $11,600 $2,040 Not Implemented
AM0629 # 02 Y:2013 02 2013 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $19,662 $0 Not Implemented
AM0629 # 01 Y:2013 01 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $36,508 $2,000 Not Implemented
UM0413 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,508 $2,500 Implemented
UM0413 # 01 Y:2012 01 2012 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES $3,930 $1,000 Implemented
UM0413 # 02 Y:2012 02 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,595 $1,000 Not Implemented
UM0413 # 04 Y:2012 04 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,256 $200 Not Implemented
UM0413 # 05 Y:2012 05 2012 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,975 $1,500 Not Implemented
UM0413 # 06 Y:2012 06 2012 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $566 $100 Not Implemented
AM0611 # 10 Y:2012 10 2012 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $180 $0 Not Implemented
AM0611 # 09 Y:2012 09 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $720 $1,900 Not Implemented
AM0611 # 08 Y:2012 08 2012 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $1,300 $1,030 Not Implemented
AM0611 # 07 Y:2012 07 2012 PAY UTILITY BILLS ON TIME $1,700 $0 Implemented
AM0611 # 06 Y:2012 06 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,200 $710 Not Implemented
AM0611 # 05 Y:2012 05 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,220 $62 Not Implemented
AM0611 # 04 Y:2012 04 2012 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,110 $2,500 Not Implemented
AM0611 # 03 Y:2012 03 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,240 $500 Implemented
AM0611 # 02 Y:2012 02 2012 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $4,320 $920 Implemented
AM0611 # 01 Y:2012 01 2012 USE EVAPORATION TO CONCENTRATE MATERIAL $10,202 $20,000 Not Implemented
LE0335 # 08 Y:2012 08 2012 INSTALL TIMERS AND/OR THERMOSTATS $516 $125 Not Implemented
LE0335 # 07 Y:2012 07 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $41,018 $44,640 Not Implemented
LE0335 # 06 Y:2012 06 2012 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,534 $3,000 Not Implemented