matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1915 # 07 Y:2019 | 07 | 2019 | OPTIMIZE PLANT POWER FACTOR | $127,719 | $54,495 | n/a |
UK1915 # 06 Y:2019 | 06 | 2019 | INSULATE BARE EQUIPMENT | $13,534 | $26,305 | n/a |
UK1915 # 05 Y:2019 | 05 | 2019 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $53,903 | $10,200 | n/a |
UK1915 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,983 | $21,695 | n/a |
UK1915 # 03 Y:2019 | 03 | 2019 | INSTALL OCCUPANCY SENSORS | $259 | $260 | n/a |
UK1915 # 02 Y:2019 | 02 | 2019 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $7,951 | $17,032 | n/a |
UK1915 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,711 | $2,510 | n/a |
SF0548 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,764 | $0 | Implemented |
SF0548 # 02 Y:2019 | 02 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $193 | $0 | Implemented |
SF0548 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $473 | $100 | Implemented |
SF0548 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,363 | $300 | Implemented |
SF0548 # 05 Y:2019 | 05 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,653 | $1,103 | Implemented |
SF0548 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,047 | $2,930 | Implemented |
SF0548 # 07 Y:2019 | 07 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,924 | $172,115 | Implemented |
WM0143 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,164 | $1,500 | Not Implemented |
WM0143 # 02 Y:2019 | 02 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,367 | $6,400 | Not Implemented |
WM0143 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,586 | $0 | Not Implemented |
WM0143 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,884 | $4,500 | Implemented |
WM0143 # 05 Y:2019 | 05 | 2019 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $3,255 | $0 | Not Implemented |
WM0143 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,250 | $0 | Not Implemented |
WM0143 # 12 Y:2019 | 12 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $979 | $0 | Not Implemented |
WM0143 # 08 Y:2019 | 08 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,815 | $2,460 | Not Implemented |
WM0143 # 09 Y:2019 | 09 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,598 | $2,000 | Not Implemented |
WM0143 # 10 Y:2019 | 10 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,438 | $928 | Not Implemented |
WM0143 # 11 Y:2019 | 11 | 2019 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,240 | $748 | Not Implemented |