Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0243 # 06 Y:1988 | 06 | 1988 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $812 | $0 | Implemented |
WI0003 # 02 Y:1987 | 02 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,286 | $0 | Implemented |
WI0003 # 03 Y:1987 | 03 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,383 | $573 | Implemented |
WI0003 # 04 Y:1987 | 04 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $263 | $398 | Implemented |
KU0227 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,771 | $4,019 | Implemented |
KU0227 # 04 Y:1987 | 04 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $1,030 | $0 | Implemented |
KU0227 # 06 Y:1987 | 06 | 1987 | COVER OPEN TANKS | $262 | $200 | Implemented |
KU0227 # 07 Y:1987 | 07 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $125 | $0 | Implemented |
KU0227 # 08 Y:1987 | 08 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $152 | $290 | Implemented |
OK0227 # 01 Y:1987 | 01 | 1987 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,433 | $3,500 | Implemented |
OK0227 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $520 | $120 | Implemented |
OK0227 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $268 | $0 | Implemented |
OK0227 # 06 Y:1987 | 06 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $513 | $305 | Implemented |
UD0235 # 01 Y:1987 | 01 | 1987 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $3,496 | $500 | Implemented |
UD0235 # 02 Y:1987 | 02 | 1987 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,497 | $0 | Implemented |
TN0306 # 01 Y:1987 | 01 | 1987 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,664 | $1,743 | Implemented |
TN0306 # 02 Y:1987 | 02 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $397 | $0 | Implemented |
TN0306 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,231 | $150 | Implemented |
TN0306 # 04 Y:1987 | 04 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $522 | $3,600 | Implemented |
TN0306 # 05 Y:1987 | 05 | 1987 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $390 | $0 | Implemented |
CO0092 # 01 Y:1987 | 01 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,461 | $500 | Implemented |
CO0092 # 02 Y:1987 | 02 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,213 | $3,000 | Implemented |
CO0092 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,081 | $250 | Implemented |
CO0092 # 04 Y:1987 | 04 | 1987 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,490 | $2,000 | Implemented |
CO0092 # 06 Y:1987 | 06 | 1987 | REDUCE VENTILATION AIR | $300 | $36 | Implemented |