Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
310
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0417 # 03 Y:1991 | 03 | 1991 | INSTALL SET-BACK TIMERS | $3,696 | $0 | Not Implemented |
TN0417 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $855 | $1,600 | Not Implemented |
TN0417 # 05 Y:1991 | 05 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,010 | $0 | Not Implemented |
TN0417 # 06 Y:1991 | 06 | 1991 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,372 | $3,285 | Not Implemented |
TN0417 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,145 | $1,476 | Not Implemented |
TN0417 # 08 Y:1991 | 08 | 1991 | DISCONNECT BALLASTS | $476 | $0 | Not Implemented |
TN0417 # 09 Y:1991 | 09 | 1991 | IMPROVE LUBRICATION PRACTICES | $267 | $0 | Not Implemented |
TN0356 # 01 Y:1988 | 01 | 1988 | USE RADIANT HEATER FOR SPOT HEATING | $17,070 | $34,560 | Implemented |
TN0356 # 02 Y:1988 | 02 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $9,024 | $8,980 | Implemented |
TN0356 # 03 Y:1988 | 03 | 1988 | KEEP LAMPS AND REFLECTORS CLEAN | $12,279 | $14,384 | Implemented |
TN0356 # 04 Y:1988 | 04 | 1988 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,846 | $6,850 | Implemented |
TN0356 # 05 Y:1988 | 05 | 1988 | IMPROVE LUBRICATION PRACTICES | $1,370 | $1,200 | Implemented |
TN0356 # 06 Y:1988 | 06 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $752 | $150 | Implemented |
TN0343 # 01 Y:1988 | 01 | 1988 | KEEP LAMPS AND REFLECTORS CLEAN | $42,911 | $23,701 | Implemented |
TN0343 # 02 Y:1988 | 02 | 1988 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $14,762 | $35,660 | Not Implemented |
TN0343 # 03 Y:1988 | 03 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,447 | $4,500 | Implemented |
TN0343 # 04 Y:1988 | 04 | 1988 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,721 | $0 | Not Implemented |
TN0343 # 05 Y:1988 | 05 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,610 | $2,000 | Implemented |
TN0343 # 06 Y:1988 | 06 | 1988 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,647 | $780 | Implemented |
TN0343 # 07 Y:1988 | 07 | 1988 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,034 | $1,300 | Implemented |
TN0306 # 01 Y:1987 | 01 | 1987 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,664 | $1,743 | Implemented |
TN0306 # 02 Y:1987 | 02 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $397 | $0 | Implemented |
TN0306 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,231 | $150 | Implemented |
TN0306 # 04 Y:1987 | 04 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $522 | $3,600 | Implemented |
TN0306 # 05 Y:1987 | 05 | 1987 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $390 | $0 | Implemented |