Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
445
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0616 # 08 Y:1997 | 08 | 1997 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $870 | $2,500 | Not Implemented |
TN0616 # 09 Y:1997 | 09 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $140 | $0 | Implemented |
NC0107 # 01 Y:1997 | 01 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $287 | $420 | Implemented |
NC0107 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,452 | $1,356 | Implemented |
NC0107 # 03 Y:1997 | 03 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $242 | $280 | Not Implemented |
NC0107 # 04 Y:1997 | 04 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $69,557 | $9,600 | Not Implemented |
NC0107 # 05 Y:1997 | 05 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $38 | $100 | Not Implemented |
NC0107 # 06 Y:1997 | 06 | 1997 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $21,230 | $15,000 | Implemented |
NC0107 # 07 Y:1997 | 07 | 1997 | USE MORE EFFICIENT ADHESIVE APPLICATORS | $16,861 | $2,000 | Not Implemented |
NC0105 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,316 | $5,062 | Not Implemented |
NC0105 # 02 Y:1996 | 02 | 1996 | INSTALL OCCUPANCY SENSORS | $1,852 | $375 | Not Implemented |
NC0105 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $449 | $2,100 | Not Implemented |
NC0105 # 04 Y:1996 | 04 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,194 | $1,520 | Not Implemented |
NC0105 # 05 Y:1996 | 05 | 1996 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,174 | $11,500 | Not Implemented |
NC0105 # 06 Y:1996 | 06 | 1996 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,508 | $3,000 | Implemented |
NC0105 # 07 Y:1996 | 07 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,655 | $5,125 | Not Implemented |
NC0105 # 08 Y:1996 | 08 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,562 | $5,464 | Not Implemented |
NC0105 # 09 Y:1996 | 09 | 1996 | COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES | $702 | $500 | Not Implemented |
NC0105 # 10 Y:1996 | 10 | 1996 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $826 | $500 | Not Implemented |
NC0105 # 11 Y:1996 | 11 | 1996 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $225 | $200 | Not Implemented |
TN0591 # 01 Y:1996 | 01 | 1996 | INSTALL SPECTRAL REFLECTORS / DELAMP | $7,095 | $21,300 | Implemented |
TN0591 # 02 Y:1996 | 02 | 1996 | CONVERT TO ELECTROSTATIC POWDER COATING | $3,817 | $10,480 | Not Implemented |
TN0591 # 03 Y:1996 | 03 | 1996 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $2,265 | $6,160 | Not Implemented |
TN0591 # 04 Y:1996 | 04 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $777 | $2,520 | Implemented |
TN0591 # 05 Y:1996 | 05 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $621 | $1,920 | Implemented |