Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
476
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2317 # 09 Y:2023 | 09 | 2023 | ADOPT IN-HOUSE MATERIAL GENERATION | $30,659 | $188,853 | Not Implemented |
UC2317 # 08 Y:2023 | 08 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,409 | $34,609 | Not Implemented |
UC2317 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,763 | $17,190 | Not Implemented |
UC2317 # 06 Y:2023 | 06 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $714 | $540 | Not Implemented |
UC2317 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,584 | $1,300 | Not Implemented |
UC2317 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,123 | $428 | Not Implemented |
UC2317 # 10 Y:2023 | 10 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $6,903 | $1,468 | Not Implemented |
UC2317 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $90,350 | $29,189 | Not Implemented |
UC2317 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,240 | $50 | Not Implemented |
UC2317 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $392 | $75 | Not Implemented |
UC2317 # 11 Y:2023 | 11 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $321,413 | $2,701,940 | Not Implemented |
UC2317 # 12 Y:2023 | 12 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,411 | $0 | Not Implemented |
CM1025 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $34,270 | $526,058 | n/a |
CM1025 # 02 Y:2023 | 02 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $5,141 | $28,827 | n/a |
CM1025 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,196 | $889 | n/a |
CM1025 # 04 Y:2023 | 04 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $2,954 | $22,704 | n/a |
CM1025 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,162 | $2,172 | n/a |
IP0180 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,666 | $1,830 | Implemented |
IP0180 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,621 | $36,055 | Implemented |
IP0180 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,158 | $32 | Implemented |
IP0180 # 04 Y:2023 | 04 | 2023 | USE FOG NOZZLES / SPRAY RINSING INSTEAD OF IMMERSION RINSING | $4,518 | $5,490 | Not Implemented |
IP0180 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,597 | $3,719 | Not Implemented |
IP0180 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,258 | $0 | Implemented |
IP0180 # 07 Y:2023 | 07 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $6,444 | $26,075 | Not Implemented |
NL0090 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,382 | $4,500 | Implemented |