IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,768

matching recommendations
Reset
SIC 353 Construction And Related Machinery
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0601 # 04 Y:2000 04 2000 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $140,000 $100,000 Not Implemented
OK0601 # 05 Y:2000 05 2000 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $29,952 $0 Not Implemented
OK0601 # 06 Y:2000 06 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $14,040 $35,000 Implemented
OK0601 # 07 Y:2000 07 2000 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE $5,829 $0 Not Implemented
AM0377 # 01 Y:2000 01 2000 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $27,190 $0 Implemented
AM0377 # 02 Y:2000 02 2000 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $11,500 $6,100 Implemented
AM0377 # 03 Y:2000 03 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,870 $500 Implemented
AM0377 # 04 Y:2000 04 2000 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $900 $1,000 Not Implemented
AM0377 # 05 Y:2000 05 2000 INSTALL OCCUPANCY SENSORS $450 $110 Implemented
AM0377 # 06 Y:2000 06 2000 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $320 $0 Implemented
AM0377 # 07 Y:2000 07 2000 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $230 $0 Implemented
AM0376 # 01 Y:2000 01 2000 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $77,809 $157,500 Not Implemented
AM0376 # 02 Y:2000 02 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $19,313 $32,300 Not Implemented
AM0376 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,410 $3,340 Implemented
AM0376 # 04 Y:2000 04 2000 TURN OFF EQUIPMENT WHEN NOT IN USE $1,250 $0 Not Implemented
AM0376 # 05 Y:2000 05 2000 ADD AREA LIGHTING SWITCHES $950 $640 Implemented
AM0376 # 06 Y:2000 06 2000 USE PHOTOCELL CONTROLS $730 $605 Implemented
AM0376 # 07 Y:2000 07 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $700 $350 Implemented
AM0376 # 08 Y:2000 08 2000 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $600 $1,030 Implemented
NV0157 # 01 Y:2000 01 2000 BURN A LESS EXPENSIVE GRADE OF FUEL $33,074 $25 Not Implemented
NV0157 # 02 Y:2000 02 2000 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $2,588 $700 Not Implemented
NV0157 # 03 Y:2000 03 2000 REUSE / RECYCLE/ SELL PAPER PRODUCTS $96 $0 Not Implemented
NV0157 # 04 Y:2000 04 2000 REUSE / RECYCLE/ SELL PAPER PRODUCTS $84 $0 Not Implemented
NV0157 # 05 Y:2000 05 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $191,450 $250,000 Not Implemented
NV0157 # 06 Y:2000 06 2000 ELIMINATE SHIFT $41,600 $7,395 Not Implemented