Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 3531 | Construction Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0610 # 05 Y:2012 | 05 | 2012 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,000 | $1,300 | Implemented |
AM0610 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,900 | $21,800 | Implemented |
AM0610 # 02 Y:2012 | 02 | 2012 | INSTALL SKYLIGHTS | $8,500 | $2,560 | Not Implemented |
AM0610 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,515 | $1,500 | Implemented |
AM0610 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $485 | $275 | Implemented |
AM0610 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $485 | $275 | Implemented |
AM0610 # 06 Y:2012 | 06 | 2012 | USE SYNTHETIC LUBRICANT | $715 | $0 | Not Implemented |
AM0610 # 04 Y:2012 | 04 | 2012 | OPTIMIZE PLANT POWER FACTOR | $6,000 | $13,190 | Not Implemented |
AM0479 # 02 Y:2005 | 02 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $7,490 | $0 | Not Implemented |
AM0479 # 11 Y:2005 | 11 | 2005 | COMBINE UTILITY METERS | $255 | $600 | Implemented |
AM0479 # 01 Y:2005 | 01 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $66,000 | $50 | Implemented |
AM0479 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,715 | $0 | Implemented |
AM0479 # 04 Y:2005 | 04 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,300 | $230 | Not Implemented |
AM0479 # 05 Y:2005 | 05 | 2005 | USE PHOTOCELL CONTROLS | $1,600 | $2,440 | Not Implemented |
AM0479 # 06 Y:2005 | 06 | 2005 | OPTIMIZE PLANT POWER FACTOR | $790 | $0 | Implemented |
AM0479 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $585 | $0 | Implemented |
AM0479 # 08 Y:2005 | 08 | 2005 | USE SYNTHETIC LUBRICANT | $445 | $0 | Implemented |
AM0479 # 09 Y:2005 | 09 | 2005 | PAY UTILITY BILLS ON TIME | $400 | $170 | Implemented |
AM0479 # 10 Y:2005 | 10 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $370 | $1,130 | Implemented |
AM0479 # 12 Y:2005 | 12 | 2005 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $585 | $12,000 | Implemented |
TA0017 # 03 Y:2001 | 03 | 2001 | PAY BILLS ON TIME TO AVOID LATE FEES | $269 | $0 | Implemented |
TA0017 # 05 Y:2001 | 05 | 2001 | USE SYNTHETIC LUBRICANT | $130 | $0 | Not Implemented |
TA0017 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $295 | $6 | Implemented |
TA0017 # 02 Y:2001 | 02 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,400 | $0 | Implemented |
TA0017 # 01 Y:2001 | 01 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,600 | $192 | Implemented |