Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

39

matching recommendations
Reset
SIC 3544 Special Dies, Tools, Jigs & Fixtures
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WM0011 # 07 Y:2012 07 2012 USE A RAG RECYCLE SERVICE $2,496 $0 Not Implemented
WM0011 # 03 Y:2012 03 2012 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $293 $265 Implemented
WM0011 # 01 Y:2012 01 2012 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $14,000 $0 Implemented
WM0011 # 09 Y:2012 09 2012 IMPROVE SPACE COMFORT CONDITIONING $2,993 $3,000 Implemented
WM0011 # 08 Y:2012 08 2012 COMBINE UTILITY METERS $1,110 $5,000 Not Implemented
WM0011 # 04 Y:2012 04 2012 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $899 $1,480 Not Implemented
WM0011 # 02 Y:2012 02 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,063 $440 Implemented
WM0011 # 06 Y:2012 06 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $357 $0 Not Implemented
WM0011 # 05 Y:2012 05 2012 INSTALL OCCUPANCY SENSORS $406 $600 Not Implemented
WI0420 # 04 Y:2002 04 2002 REPLACE CLOTH RAGS WITH PAPER TOWELS $1,012 $0 Not Implemented
WI0420 # 08 Y:2002 08 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $315 $0 Not Implemented
WI0420 # 03 Y:2002 03 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,832 $1,601 Not Implemented
WI0420 # 02 Y:2002 02 2002 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $6,868 $933 Implemented
WI0420 # 01 Y:2002 01 2002 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $41,849 $203,000 Not Implemented
WI0420 # 05 Y:2002 05 2002 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $993 $2,094 Not Implemented
WI0420 # 06 Y:2002 06 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $576 $640 Implemented
WI0420 # 07 Y:2002 07 2002 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $315 $543 Implemented
WI0282 # 02 Y:1996 02 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $619 $0 Not Implemented
WI0282 # 03 Y:1996 03 1996 INSTALL SET-BACK TIMERS $2,726 $800 Implemented
WI0282 # 04 Y:1996 04 1996 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $1,019 $0 Implemented
WI0282 # 05 Y:1996 05 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $557 $283 Implemented
WI0282 # 06 Y:1996 06 1996 INSTALL OCCUPANCY SENSORS $375 $375 Implemented
WI0282 # 07 Y:1996 07 1996 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $358 $640 Not Implemented
WI0282 # 08 Y:1996 08 1996 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $212 $0 Implemented
WI0282 # 09 Y:1996 09 1996 INSULATE BARE EQUIPMENT $107 $149 Not Implemented