Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
424
matching recommendationsSIC | 3545 | Machine Tool Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0289 # 06 Y:2000 | 06 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $301 | $380 | Not Implemented |
AS0289 # 07 Y:2000 | 07 | 2000 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $387 | $60 | Not Implemented |
AS0289 # 08 Y:2000 | 08 | 2000 | CLEAR AND RENT EXISTING SPACE | $29,000 | $650 | Implemented |
BD0167 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,161 | $500 | n/a |
BD0167 # 02 Y:2000 | 02 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $776 | $1,750 | n/a |
BD0167 # 03 Y:2000 | 03 | 2000 | INSTALL OCCUPANCY SENSORS | $529 | $600 | n/a |
BD0167 # 04 Y:2000 | 04 | 2000 | USE EVAPORATION TO CONCENTRATE MATERIAL | $924 | $3,400 | n/a |
BD0167 # 05 Y:2000 | 05 | 2000 | MINIMIZE WATER USAGE | $328 | $1,080 | n/a |
BD0167 # 06 Y:2000 | 06 | 2000 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $273,586 | $375,000 | n/a |
AR0176 # 01 Y:1999 | 01 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $659 | $1,135 | Not Implemented |
AR0176 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,051 | $360 | Not Implemented |
AR0176 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30 | $287 | Not Implemented |
AR0176 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $946 | $2,237 | Not Implemented |
AR0176 # 05 Y:1999 | 05 | 1999 | USE LESS WASTEFUL PACKAGING | $2,479 | $1,300 | Not Implemented |
AR0176 # 06 Y:1999 | 06 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $8,964 | $17,500 | Not Implemented |
BD0137 # 01 Y:1999 | 01 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,412 | $4,890 | Not Implemented |
BD0137 # 02 Y:1999 | 02 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,871 | $0 | Not Implemented |
BD0137 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,635 | $225 | Implemented |
BD0137 # 04 Y:1999 | 04 | 1999 | INSTALL OCCUPANCY SENSORS | $1,559 | $900 | Not Implemented |
BD0137 # 05 Y:1999 | 05 | 1999 | USE SYNTHETIC LUBRICANT | $1,173 | $600 | Not Implemented |
BD0137 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $966 | $969 | Not Implemented |
BD0137 # 07 Y:1999 | 07 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $735 | $500 | Not Implemented |
BD0137 # 08 Y:1999 | 08 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $662 | $380 | Not Implemented |
BD0137 # 09 Y:1999 | 09 | 1999 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $2,707 | $10,000 | Implemented |
BD0137 # 10 Y:1999 | 10 | 1999 | MINIMIZE WATER USAGE | $793 | $1,540 | Not Implemented |