Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,555
matching recommendationsSIC | 355 | Special Industry Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0610 # 06 Y:2024 | 06 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $2,691 | $5,108 | n/a |
UF0610 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $4,345 | $2,330 | n/a |
UF0610 # 10 Y:2024 | 10 | 2024 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $15,675 | $25,000 | n/a |
UF0610 # 09 Y:2024 | 09 | 2024 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $54,895 | $0 | n/a |
UF0610 # 08 Y:2024 | 08 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $1,315 | $4,000 | n/a |
UF0610 # 02 Y:2024 | 02 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $28,883 | $18,333 | n/a |
UF0610 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $108,899 | $322,608 | n/a |
UF0610 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $9,119 | $36,000 | n/a |
UF0610 # 11 Y:2024 | 11 | 2024 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $4,482 | $3,330 | n/a |
UC2317 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $90,350 | $29,189 | n/a |
UC2317 # 10 Y:2023 | 10 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $6,903 | $1,468 | n/a |
UC2317 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $392 | $75 | n/a |
UC2317 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,763 | $17,190 | n/a |
UC2317 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,240 | $50 | n/a |
UC2317 # 11 Y:2023 | 11 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $321,413 | $2,701,940 | n/a |
UC2317 # 12 Y:2023 | 12 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,411 | $0 | n/a |
UC2317 # 09 Y:2023 | 09 | 2023 | ADOPT IN-HOUSE MATERIAL GENERATION | $30,659 | $188,853 | n/a |
UC2317 # 08 Y:2023 | 08 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,409 | $34,609 | n/a |
UC2317 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,584 | $1,300 | n/a |
UC2317 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,123 | $428 | n/a |
UC2317 # 06 Y:2023 | 06 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $714 | $540 | n/a |
DL0233 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $699 | $319 | n/a |
DL0233 # 02 Y:2024 | 02 | 2024 | USE OPTIMUM TEMPERATURE | $516 | $0 | n/a |
DL0233 # 03 Y:2024 | 03 | 2024 | USE OPTIMUM TEMPERATURE | $769 | $1,439 | n/a |
DL0233 # 01 Y:2024 | 01 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $265 | $0 | n/a |