IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

42

matching recommendations
Reset
SIC 356 General Industrial Machinery
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0525 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $185 $400 Not Implemented
WI0525 # 04 Y:2006 04 2006 USE SYNTHETIC LUBRICANT $3,880 $0 Not Implemented
WI0525 # 03 Y:2006 03 2006 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $4,600 $0 Not Implemented
WI0525 # 02 Y:2006 02 2006 MODIFY WORKLOAD $11,666 $9,000 Not Implemented
WI0525 # 01 Y:2006 01 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,775 $23,040 Not Implemented
UD0747 # 05 Y:2006 05 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,322 $14,256 Implemented
UD0747 # 09 Y:2006 09 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,678 $0 Not Implemented
UD0747 # 04 Y:2006 04 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $20,997 $22,960 Not Implemented
UD0747 # 03 Y:2006 03 2006 USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD $23,000 $1,200 Not Implemented
UD0747 # 02 Y:2006 02 2006 DEVELOP STANDARD OPERATING PROCEDURES $29,600 $32,000 Implemented
UD0747 # 01 Y:2006 01 2006 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $182,400 $85,000 Not Implemented
UD0747 # 06 Y:2006 06 2006 USE OPTIMUM THICKNESS INSULATION $4,800 $9,030 Not Implemented
UD0747 # 07 Y:2006 07 2006 INSULATE BARE EQUIPMENT $3,215 $1,995 Not Implemented
UD0747 # 11 Y:2006 11 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,209 $1,800 Not Implemented
UD0747 # 08 Y:2006 08 2006 INSTALL TIMERS AND/OR THERMOSTATS $3,095 $760 Not Implemented
UD0747 # 13 Y:2006 13 2006 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $909 $1,000 Not Implemented
UD0747 # 10 Y:2006 10 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,554 $4,920 Not Implemented
UD0747 # 12 Y:2006 12 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $920 $0 Not Implemented
UD0747 # 14 Y:2006 14 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $480 $81 Not Implemented
TA0117 # 01 Y:2006 01 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,020 $7,980 Implemented
TA0117 # 02 Y:2006 02 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,208 $5,065 Implemented
TA0117 # 03 Y:2006 03 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,925 $9 Implemented
TA0117 # 04 Y:2006 04 2006 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $478 $0 Implemented
TA0117 # 05 Y:2006 05 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $2,356 $0 Implemented
TA0117 # 06 Y:2006 06 2006 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $45,290 $22,980 Not Implemented