Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
286
matching recommendationsSIC | 3568 | Power Transmission Equipment, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0576 # 05 Y:1995 | 05 | 1995 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $20,855 | $66,000 | Not Implemented |
GT0575 # 01 Y:1995 | 01 | 1995 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,620 | $0 | Not Implemented |
GT0575 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,000 | $0 | Not Implemented |
GT0575 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $580 | $980 | Implemented |
GT0575 # 04 Y:1995 | 04 | 1995 | USE PHOTOCELL CONTROLS | $670 | $59 | Implemented |
GT0575 # 05 Y:1995 | 05 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $120 | $232 | Not Implemented |
MA0337 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,934 | $44,000 | Implemented |
MA0337 # 02 Y:1995 | 02 | 1995 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $4,708 | $5,000 | Not Implemented |
MA0337 # 03 Y:1995 | 03 | 1995 | ELIMINATE THIRD SHIFT | $4,455 | $0 | Not Implemented |
MA0337 # 04 Y:1995 | 04 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $850 | $800 | Not Implemented |
MA0337 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $750 | $1,200 | Implemented |
MA0337 # 06 Y:1995 | 06 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $484 | $0 | Not Implemented |
UD0453 # 01 Y:1995 | 01 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,324 | $250 | Not Implemented |
UD0453 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,640 | $0 | Implemented |
UD0453 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $656 | $5,000 | Not Implemented |
UD0453 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $894 | $2,000 | Not Implemented |
UD0453 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,297 | $2,880 | Not Implemented |
NC0048 # 01 Y:1995 | 01 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,504 | $0 | Not Implemented |
NC0048 # 02 Y:1995 | 02 | 1995 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $112 | $100 | Not Implemented |
NC0048 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $195 | $38 | Not Implemented |
NC0048 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $589 | $180 | Not Implemented |
NC0048 # 05 Y:1995 | 05 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,762 | $1,000 | Not Implemented |
NC0048 # 06 Y:1995 | 06 | 1995 | INSULATE BARE EQUIPMENT | $2,212 | $6,061 | Not Implemented |
MA0258 # 01 Y:1992 | 01 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,096 | $0 | Not Implemented |
MA0258 # 02 Y:1992 | 02 | 1992 | INSULATE BARE EQUIPMENT | $954 | $314 | Not Implemented |