Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
518
matching recommendationsSIC | 3585 | Refrigeration And Heating Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0486 # 07 Y:2005 | 07 | 2005 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $175 | $700 | Implemented |
AS0393 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,557 | $210 | Implemented |
AS0393 # 05 Y:2005 | 05 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,250 | $12,278 | Implemented |
AS0393 # 06 Y:2005 | 06 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,527 | $70 | Implemented |
AS0393 # 07 Y:2005 | 07 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,152 | $1,260 | Implemented |
AS0393 # 08 Y:2005 | 08 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $968 | $3,000 | Implemented |
AS0393 # 10 Y:2005 | 10 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $108 | $224 | Implemented |
GT0789 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $63,136 | $0 | Implemented |
GT0789 # 02 Y:2004 | 02 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $3,090 | $1,824 | Implemented |
GT0789 # 03 Y:2004 | 03 | 2004 | DISCONNECT BALLASTS | $639 | $645 | Implemented |
GT0789 # 05 Y:2004 | 05 | 2004 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $21,400 | $9,700 | Implemented |
GT0789 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,160 | $2,400 | Implemented |
GT0789 # 07 Y:2004 | 07 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,570 | $6,000 | Implemented |
GT0789 # 09 Y:2004 | 09 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $55,800 | $198,000 | Implemented |
OK0692 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,239 | $2,275 | Implemented |
OK0692 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,221 | $8,625 | Implemented |
OK0692 # 06 Y:2004 | 06 | 2004 | INSTALL SET-BACK TIMERS | $81,447 | $10,000 | Implemented |
OK0692 # 07 Y:2004 | 07 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $8,800 | $0 | Implemented |
OK0692 # 10 Y:2004 | 10 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,577 | $11,882 | Implemented |
OK0691 # 02 Y:2004 | 02 | 2004 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $270,439 | $2,825 | Implemented |
OK0691 # 03 Y:2004 | 03 | 2004 | INSTALL SET-BACK TIMERS | $6,531 | $3,832 | Implemented |
OK0691 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,036 | $559 | Implemented |
OK0691 # 05 Y:2004 | 05 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $265 | $0 | Implemented |
OK0691 # 07 Y:2004 | 07 | 2004 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $886 | $139 | Implemented |
OK0689 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $1,079 | $2,156 | Implemented |