Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 3599 | Industrial Machinery, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0228 # 07 Y:1999 | 07 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,067 | $0 | Implemented |
IA0228 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $226 | $50 | Implemented |
IA0228 # 05 Y:1999 | 05 | 1999 | INSTALL OCCUPANCY SENSORS | $424 | $865 | Not Implemented |
IA0228 # 04 Y:1999 | 04 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $468 | $50 | Not Implemented |
IA0228 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $525 | $2,320 | Implemented |
IA0228 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $634 | $581 | Implemented |
IA0228 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,046 | $344 | Implemented |
IA0211 # 02 Y:1998 | 02 | 1998 | INSTALL OCCUPANCY SENSORS | $2,579 | $1,064 | Implemented |
IA0211 # 07 Y:1998 | 07 | 1998 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $24,960 | $25,440 | Implemented |
IA0211 # 06 Y:1998 | 06 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $57,028 | $800 | Implemented |
IA0211 # 05 Y:1998 | 05 | 1998 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $8,750 | $1,448 | Not Implemented |
IA0211 # 04 Y:1998 | 04 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $20,305 | $2,250 | Implemented |
IA0211 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,935 | $700 | Implemented |
IA0211 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,647 | $53,193 | Not Implemented |
IA0130 # 05 Y:1995 | 05 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $944 | $165 | Not Implemented |
IA0130 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,157 | $22,800 | Not Implemented |
IA0130 # 02 Y:1995 | 02 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $607 | $0 | Implemented |
IA0130 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,470 | $342 | Implemented |
IA0130 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,472 | $2,090 | Implemented |
IA0130 # 06 Y:1995 | 06 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $769 | $25 | Not Implemented |
IA0130 # 07 Y:1995 | 07 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,903 | $669 | Implemented |
IA0130 # 08 Y:1995 | 08 | 1995 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,249 | $1,030 | Implemented |
IA0130 # 09 Y:1995 | 09 | 1995 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $6,542 | $34,200 | Implemented |
IA0130 # 10 Y:1995 | 10 | 1995 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $8,419 | $5,456 | Not Implemented |
IA0130 # 11 Y:1995 | 11 | 1995 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,287 | $0 | Implemented |