Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
249
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0189 # 07 Y:1983 | 07 | 1983 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $37,600 | $20,000 | Not Implemented |
GT0186 # 01 Y:1983 | 01 | 1983 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $10,060 | $25,100 | Not Implemented |
GT0186 # 02 Y:1983 | 02 | 1983 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,720 | $18,880 | Not Implemented |
GT0186 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,511 | $6,189 | Not Implemented |
GT0186 # 04 Y:1983 | 04 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,261 | $500 | Not Implemented |
GT0171 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,190 | $16,000 | Not Implemented |
GT0171 # 02 Y:1983 | 02 | 1983 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,260 | $20,600 | Not Implemented |
GT0171 # 03 Y:1983 | 03 | 1983 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,142 | $9,853 | Not Implemented |
GT0171 # 04 Y:1983 | 04 | 1983 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,750 | $12,500 | Not Implemented |
GT0171 # 05 Y:1983 | 05 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,760 | $1,029 | Not Implemented |
GT0171 # 06 Y:1983 | 06 | 1983 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $5,660 | $3,000 | Not Implemented |
GT0171 # 07 Y:1983 | 07 | 1983 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $613 | $2,470 | Not Implemented |
GT0148 # 01 Y:1982 | 01 | 1982 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,325 | $5,549 | Not Implemented |
GT0148 # 02 Y:1982 | 02 | 1982 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $195 | $500 | Not Implemented |
GT0148 # 03 Y:1982 | 03 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,080 | $833 | Not Implemented |
GT0148 # 04 Y:1982 | 04 | 1982 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $16,150 | $10,000 | Not Implemented |
GT0148 # 05 Y:1982 | 05 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,136 | $375 | Not Implemented |
GT0117 # 01 Y:1982 | 01 | 1982 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,518 | $2,760 | Not Implemented |
GT0117 # 02 Y:1982 | 02 | 1982 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $7,669 | $5,792 | Not Implemented |
GT0117 # 03 Y:1982 | 03 | 1982 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $7,298 | $1,500 | Not Implemented |
GT0117 # 04 Y:1982 | 04 | 1982 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $310 | $500 | Not Implemented |
GT0118 # 01 Y:1982 | 01 | 1982 | AIR CONDITION ONLY SPACE NECESSARY | $5,952 | $573 | Not Implemented |
GT0118 # 03 Y:1982 | 03 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,187 | $608 | Not Implemented |
GT0118 # 04 Y:1982 | 04 | 1982 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,676 | $198 | Not Implemented |