Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,701
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0790 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $120 | $116 | n/a |
LS2410 # 01 Y:2024 | 01 | 2024 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,967 | $75 | Implemented |
LS2410 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $34,951 | $21,000 | Implemented |
LS2410 # 03 Y:2024 | 03 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $4,159 | $12,500 | Implemented |
LS2410 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $104,382 | $480,480 | Not Implemented |
NT0028 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,367 | $0 | Implemented |
NT0028 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $22,571 | $9,184 | Not Implemented |
NT0028 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,586 | $20,775 | Implemented |
NT0028 # 05 Y:2024 | 05 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $27,609 | $10,000 | Implemented |
NT0028 # 06 Y:2024 | 06 | 2024 | OPTIMIZE PLANT POWER FACTOR | $11,431 | $6,584 | Not Implemented |
NT0028 # 07 Y:2024 | 07 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $21,431 | $520 | Not Implemented |
NT0028 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,518 | $5,609 | Implemented |
OK1113 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,139 | $4,760 | Not Implemented |
OK1113 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,798 | $1,675 | Not Implemented |
OK1113 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $25,346 | $210,600 | Not Implemented |
OK1113 # 04 Y:2024 | 04 | 2024 | INSTALL SUB-METERING EQUIPMENT | $1,500 | $1,100 | Not Implemented |
OK1113 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $125 | $611 | Not Implemented |
WM0223 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,737 | $8,466 | Not Implemented |
WM0223 # 02 Y:2024 | 02 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,472 | $5,580 | Not Implemented |
WM0223 # 03 Y:2024 | 03 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,062 | $994 | Not Implemented |
WM0223 # 04 Y:2024 | 04 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $971 | $0 | Not Implemented |
WM0223 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $946 | $0 | Not Implemented |
WM0223 # 06 Y:2024 | 06 | 2024 | USE PHOTOCELL CONTROLS | $406 | $200 | Not Implemented |
WM0222 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,099 | $21,586 | Not Implemented |
WM0222 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,848 | $12,763 | Not Implemented |